MahaRERA Property Intelligence · Mumbai Suburban

SEASONS TRIMURTI

P51800052227 · SANTACRUZ WEST · promoter Seasons Avenues Properties

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP51800052227
Registered on31 Jul 2023
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Seasons Avenues Properties is the promoter of record on 8 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 11 homes filed with MahaRERA, 1 are sold/booked and 10 remain available (~9% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹25.50 Cr in agreement value so far. Of that, ₹24.98 Cr (~98%) is already collected, ₹52.37 Lakh receivable — a read on how far along these sales really are. Note: the project registers 51 homes in total, but this sold/unsold inventory filing covers only 11 of them — the other 40 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 101001A2,959 sqft (274.91 sqm)₹12.73 Cr
Floor 101001B2,959 sqft (274.91 sqm)₹12.73 Cr
Floor 111101A2,959 sqft (274.91 sqm)₹13.34 Cr
Floor 111101B2,959 sqft (274.91 sqm)₹13.34 Cr
Floor 121201A2,959 sqft (274.91 sqm)₹13.34 Cr
Floor 121201B2,959 sqft (274.91 sqm)₹13.34 Cr
Floor 141401A2,874 sqft (267.01 sqm)₹12.96 Cr
Floor 141401B2,888 sqft (268.34 sqm)₹13.02 Cr
Floor 151501A3,924 sqft (364.54 sqm)₹17.69 Cr
Floor 151501B833 sqft (77.43 sqm)₹3.76 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18 and 51 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SEASONS TRIMURTI1G+1851-

Unit mix on the filing: 51 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at SANTACRUZ WEST, NORTH AVENUE ROAD, Andheri, Mumbai Suburban, 400054. Per the filed land record, the plot is bounded to the north by NORTH AVENUE ROAD, to the south by PLOTS BEARING NO412 AND 418, to the east by SAROJINI ROAD and to the west by 15TH ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Santacruz West

Woodstock Gardens
possession by Oct 2026 · Woodstock Realties Private Limited
Artteza
possession by Nov 2026 · Sunvision Estates
M.K Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Shaista Majid Khan
Cyrilyn
possession by Dec 2026 · Not Available
JAY Krupa Sadan BY Shree Hari Realty
possession by Dec 2026 · Shree Hari Realty
Orchid Vasundhara
possession by Dec 2026 · Orchid Builtcon Pvt. Ltd.

Major developers building in Santacruz West

Other RERA-registered projects in Mumbai Suburban

Seasons- Wing F
possession by Dec 2028 · Joynest Premises Private Limited
Second Avenue Phase 1
declared completion Dec 2025 · Atul Projects Realty Private Limited
Sector R 3 Mhada
declared completion Dec 2017 · Guruashish Construction Private Limited
Sector R-3 Of Siddhartha Nagar Patra Chawl Redevelopment
possession by Mar 2027 · Mumbai Housing And Area Development Boar
Seema Rajdhani
declared completion Sep 2025 · Seema Properties AND Builders LLP
Seeron Dyo
possession by Jun 2027 · Amrapali Heights CO OP Housing Society L

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026