MahaRERA Property Intelligence · Mumbai Suburban

SERENO-A, Omkar International District

P51800017369 · Western Suburbs · promoter Omkar Ventures Pvt

Certificate SignedDue 30 Mar 2025

Delivery & Registration

MahaRERA registrationP51800017369
Registered on09 Aug 2018
Promoter-declared completion30 Mar 2025
Current statusCertificate Signed
Against todayabout 16 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Omkar Ventures Pvt is the promoter of record on 151 projects, of which 21 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+26.

BuildingWingsFloorsDeclared completion
SERENO-A11G+2631 Mar 2023
SERENO-A21G+2631 Mar 2023
SERENO-B31-31 Mar 2023

Complaints & Orders

17 complaints are on the MahaRERA record for this project, with orders passed in 16. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000005695517/11/2018Vanora Vaz vs Omkar Ventures Pvt. Ltdorder passed
CC00600000011086410/09/2019Vineeta Dsouza vs Omkar Ventures Pvt Ltdorder passed
CC00600000018206004/01/2020Sarada Prasad Dash vs omkar serenoorder passed
CC00600000019690004/05/2021Dhaval Rakesh Patel vs Omkar Ventures Private Limitedorder passed
CC00600000019539701/01/2021Sandeep Indurkar vs Omkar Ventures Private Limitedorder passed
CC00600000019569820/01/2021Anant Keshav Vanjare vs Omkar Ventures Pvt. Ltd.order passed
CC00600000019603519/02/2021Dhaval Rakesh Patel vs Omkar Realtors & Developers Pvt. Ltdorder passed
CC00600000019783230/07/2021Kamal Manohar Jumani vs Omkar Ventures Pvt. Ltd.order passed
CC00600000019783430/07/2021Sunil Jaikishan Aidasani vs Omkar Ventures Pvt. Ltd.order passed
CC00600000019796512/08/2021Mr. Anand Chaturvedi vs M/s Omkar Ventures Pvt Ltdorder passed
CC00600000025192521/07/2022Mr Amit Rasiklal Chaturvedi And Mrs Ritu Amit Chaturvedi vs Omkar Ventures Pvt. Ltd.order passed
CC00600000039769006/10/2023Ravi Ramesh Bhatia vs Omkar Ventures Pvt. Ltdorder passed
CC00600000059133527/07/2024Veena Anand Nimangre vs Omkar Ventures Pvt Ltdorder passed
CC00600000059133627/07/2024Veena Anand Nimangre vs Omkar Ventures Pvt Ltdorder passed
CC1240080016/11/2024Rucha Dattatray Panchwagh vs Omkar Ventures Pvt. Ltd.order passed
CC1240040112/10/2024ASHRAF ABDUL JABBAR khan vs Omkar Ventures Pvt. Ltd.order passed
CC1250299925/08/2025Yogesh Agarwal vs Aspect Buildcon LLPpending / no order on file

Legal & Litigation

The promoter has declared 28 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court3522013Matter Adjourned As Per High Court Cims There Is No Adverse Order
City Civil Court Dindoshi11092017Matter Adjourned As Per City Civil Court Dindoshi Cause List There Is No Adverse Order
City Civil Court Dindoshi25572017Matter Adjourned As Per City Civil Court Dindoshi Cause List There Is No Adverse Order
City Civil Court Dindoshi3392017Matter Adjourned As Per City Civil Court Dindoshi Cause List There Is No Adverse Order
City Civil Court Dindoshi2006052018Matter Adjourned As Per City Civil Court Dindoshi Cause List There Is No Adverse Order
Small Causes Court2622016Matter Adjourned As Per Small Causes Court Cause List There Is No Adverse Order
Maharashtra Real Estate Regulatory AuthorityAT00600000000103652018Matter Adjourned As Per Rera Cause List There Is No Adverse Order
Apex Grievance Redressal Committee792017Matter Adjourned As Per Agrc Cause List There Is No Adverse Order
High Court Of Bombay4142017For Hearing
High Court Of Bombay382015For Hearing
High Court Of Bombay12212018For Hearing
High Court Of Bombay1202017For Hearing
City Civil Court Dindoshi20962018For Hearing
City Civil Court Dindoshi20972018For Hearing
City Civil Court Dindoshi20982018For Hearing
City Civil Court Dindoshi20992018For Hearing
City Civil Court Dindoshi21172018For Hearing
City Civil Court Dindoshi19182018For Hearing
City Civil Court Dindoshi19192018For Hearing
Bhoiwada Dadar Mumbai28282018For Hearing
Bhoiwada Dadar Mumbai28292018For Hearing
Bhoiwada Dadar Mumbai28272018For Hearing
Bhoiwada Dadar Mumbai29562018For Hearing
Bhoiwada Dadar Mumbai29572018For Hearing
Bhoiwada Dadar Mumbai32252018For Hearing
Bhoiwada Dadar Mumbai07000342019For Hearing
Bhoiwada Dadar Mumbai251/SS2019For Hearing
National Company Law Tribunal Mumbai Bench Mumbai35212019For Hearing

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202430 Mar 2025The reasons for seeking extension which were beyond the control of Promoter are briefly set out hereunder: 1. Discontinuation of Subvention Scheme 2. Economic downturn and Demon

Location, Land & Connectivity

Located at Western Suburbs, Off Western Express Highway, Ward FNorth, Mumbai City, 400060. Per the filed land record, the plot is bounded to the north by 431 pt, to the south by 431 pt 349 pt, to the east by 351 pt and to the west by 431 pt. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Omkar Ventures Pvt. Ltd. is the promoter on 5 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Omkar Ventures Pvt. Ltd.

Omkar Ventures Pvt. Ltd.
Not filing quarterly progress reportsMumbai Suburban
Omkar Ventures Pvt. Ltd.
Not filing quarterly progress reportsMumbai Suburban
Omkar Ventures Pvt. Ltd.
Not filing quarterly progress reportsMumbai Suburban
Omkar Ventures Pvt. Ltd.
Not filing quarterly progress reportsMumbai Suburban

Other RERA-registered projects in Jogeshwari East

Rose Blossom Chsl
possession by Aug 2026 · Vini Developers
Satyam
possession by Aug 2026 · Poddar Infracon Private Limited
Samarpan
possession by Sep 2026 · L K Infracon LLP
Prem Builders
possession by Oct 2026 · Prem Builders
Aim Heritage
possession by Dec 2026 · M/s Aim Realtors Private Limited
AIM Paradise
possession by Dec 2026 · S.k. Enterprises

Major developers building in Jogeshwari East

Other RERA-registered projects in Mumbai Suburban

Sereno-B, Omkar International District
declared completion Mar 2025 · Omkar Ventures Pvt. Ltd.
Serenova
possession by May 2029 · Kolte-Patil Developers Limited
Seth Residency
declared completion Jun 2021 · Ranapratap Kedarnath Tiwari
Sethia Aashray-Phase 1
possession by Jun 2027 · Aakash Developers
Sethia Darshan
possession by Dec 2026 · Sethia Infrastructure PVT LTD
Sethia Grandeur
declared completion Jun 2022 · K Maniar

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026