Mumbai/Project record

MahaRERA · the public record

Siddhivinayak Vastu

CHINCPOKALI,MAXGAON · SIDDHIVINAYAK CONSTRUCTION PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900007574

Delivery and registration

When is the project declared for completion?

Siddhivinayak Vastu is registered with MahaRERA as P51900007574 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900007574
Registered on17 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Siddhivinayak Vastu record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Siddhivinayak Vastu in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
Siddhivinayak vastu1G+2031 Dec 2018

Legal and disputes

What disputes are disclosed?

13 complaints are on the MahaRERA record for Siddhivinayak Vastu, with orders passed in 13 of them.

13complaints

13with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000008954925/06/2019Sumedha Fiscal Services Limited vs Siddhivinayak Constructions Private Limitedorder passed
CC00600000010035802/08/2019Om Shankar Trade Fin Private Limited vs Siddhivinayak Constructions Private Limitedorder passed
CC00600000010037131/10/2019Devvrat Gaggar vs Siddhivinayak Constructions Private Limitedorder passed
CC00600000018199010/01/2020Sumedha Fiscal Services Limited vs Siddhivinayak Constructions Private Limitedorder passed
CC00600000018199426/06/2020Om Shankar Trade Fin Private Limited vs Siddhivinayak Constructions Private Limitedorder passed
CC00600000018199525/06/2020Devvrat Gaggar vs Siddhivinayak Constructions Private Limitedorder passed
CC00600000029255605/09/2022Sumedha Fiscal Services vs Siddhivinayak Constructions Private Limitedorder passed
CC00600000019787603/08/2021Ankit Shah vs Siddhivinayak Construction Pvt. Ltd.order passed
CC00600000019889130/10/2021Ankit Shah vs Siddhivinayak Construction Pvt. Ltd.order passed
CC00600000019904515/11/2021Bhavika Siddharth Shah vs Siddhivinayak Construction Pvt. Ltd.order passed
CC00600000019904615/11/2021Bhavika Siddharth Shah vs Siddhivinayak Construction Pvt. Ltd.order passed
CC00600000042871204/01/2024DEVVRAT GAGGAR vs SIDDHIVINAYAK CONSTRUCTIONS PRIVATE LIMITEDorder passed
CC00600000042871904/01/2024Om Shankar Trade Fin Private Limited vs SIDDHIVINAYAK CONSTRUCTIONS PRIVATE LIMITEDorder passed

Location, Land & Connectivity

Located at CHINCPOKALI,MAXGAON, TELLAY GULLY, Mumbai City, Mumbai City, 400012. Per the filed land record, the plot is bounded to the north by Dattaram lad marg, to the south by Teli Gully, to the east by 826 822 and to the west by 817. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport8 km
Nariman Point / Fort11 km
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Parel

Inspire
possession by Sep 2026 · R K Constructions
K RAS Residency
possession by Sep 2026 · K RAS Group
Kinjal Pride
possession by Oct 2026 · Hi Rock Construction Pvt Ltd
Bhivawani Chawl
possession by Dec 2026 · MS Radhakrishna Developer
Bhoiwada Chandra Bhuvan CHS Ltd
possession by Dec 2026 · Avadhoot Techno Consultant And Engineers
Ruparel Jewel
possession by Dec 2026 · Renuka Realtors

Major developers building in Parel

Other RERA-registered projects in Mumbai City

Sidheshwar Royale
declared completion Mar 2026 · M/S YUG Developers
Sigma Garnet
possession by Dec 2026 · Colo Color Private Limited
Signare
possession by Sep 2026 · Tejukaya Buildcon
Signature
possession by Dec 2026 · Prabhat Sadan Properties Private Limited
Sila Tower
possession by Dec 2031 · Sila Offices Private Limiited
Silver Heights
possession by Dec 2027 · Kshama Builders & Developers Private

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026