Mumbai/Project record

MahaRERA · the public record

SIGMA EMERALD

ANDHERI · SIGMA REALTORS (INDIA) PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 Aug 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Aug 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800009738

Delivery and registration

When is the project declared for completion?

SIGMA EMERALD is registered with MahaRERA as P51800009738 and the promoter has declared completion for 28 Aug 2022.

28 Aug 2022

declared completion

49months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800009738
Registered on22 Aug 2017
Promoter-declared completion28 Aug 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SIGMA EMERALD record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sigma Realtors (India) is the promoter of record on 27 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

27projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SIGMA EMERALD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
SIGMA EMERALD WING A AND WING B1G+1930 Jun 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at ANDHERI, ANDHERI, Borivali, Mumbai Suburban, 400055. Per the filed land record, the plot is bounded to the north by NAZMAHEPTULLA COMMUNITY HALL, to the south by BLOCK 6 MAHADA COLONY, to the east by WESTERN EXPRESS HIGHWAY and to the west by GURU NARAYAN ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport2 km
Bandra Kurla Complex (BKC)3 km
Andheri MIDC / SEEPZ6 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district9 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Santacruz East

Pruthi Annexe
possession by Sep 2026 · Raja Developers
Crystal Avenue
possession by Nov 2026 · Eternia Realty
Vaibhav Heights
possession by Dec 2026 · RSN Balaji Realtors P LTD
Ambit Vista
possession by Dec 2026 · Ambit Builders & Developers
Atmiya Centria
possession by Dec 2026 · Upturn Properties LLP
Crescent Nexus
possession by Dec 2026 · Ascent Infraspace Private Limited

Other RERA-registered projects in Mumbai Suburban

Sigma Jade
possession by Dec 2028 · Niketan Ventures Private Limited
Sigma Pearl
declared completion May 2026 · Ashapura Shelters Private Limited
Sigma Solitaire
possession by Dec 2027 · Sigma Happy Homes LLP
Signature
declared completion Jul 2018 · Lakhani Builders PVT LTD
Signature
possession by Mar 2028 · Mangal Buildhome Private Limited
Signature Business Park
declared completion Dec 2022 · Swastik Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026