Mumbai/Project record

MahaRERA · the public record

SUKHMANI

Mumbai Suburban · MOONLAND BUILDERS PVT.LTD.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800005774

Delivery and registration

When is the project declared for completion?

SUKHMANI is registered with MahaRERA as P51800005774 and the promoter has declared completion for 30 Mar 2026.

30 Mar 2026

declared completion

6months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800005774
Registered on14 Aug 2017
Promoter-declared completion30 Mar 2026
Current statusCertificate Signed
Against todayabout 6 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SUKHMANI record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SUKHMANI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
SUKHMANI1G+17-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for SUKHMANI, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000035205/09/2017sukhmani society member vs moonland builder pvt ltd, karthik bhatt associatesorder passed
CC00600000019869519/10/2021hemant gupta vs moonland builders pvt ltdorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court628/20172017Order To State Government

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400049. Per the filed land record, the plot is bounded to the north by HILL CREST, to the south by FAIRYLAND, to the east by AMREET JEEVAN and to the west by 10TH ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ5 km
Chhatrapati Shivaji Int'l Airport5 km
Bandra Kurla Complex (BKC)7 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district13 km
Nariman Point / Fort21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Juhu

Elenora
possession by Sep 2026 · Parinee VIR Bhuvan Redevelopment Private
K L Valeria
possession by Sep 2026 · K L Housing LLP
Valletta
possession by Sep 2026 · K Raheja Corp Real Estate Private Limite
Maestro
possession by Nov 2026 · K Raheja Corp Real Estate Private Limite
Aditya Chsl
possession by Dec 2026 · Shree Mahavir Developers
Gurukrupa Alaknanda
possession by Dec 2026 · Gurukrupa Realcon Infrastructure Develop

Major developers building in Juhu

Other RERA-registered projects in Mumbai Suburban

Sukhsagar Heights
possession by May 2028 · Vitrag Infra Projects LLP
Sukoon SRA CHS LTD-Wing-A. /western Heights CTS 394-B&C-Wing
possession by Dec 2026 · M V Q Developers
Sultanabad Apartment
declared completion Dec 2024 · S. E. Builders
Sultanbad Sadan
declared completion May 2023 · Fortune Realty
Sumer Life
possession by Dec 2027 · Sumer Corporation
Sumit Bhakti
possession by Mar 2028 · Sumit Pragati Ventures LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026