MahaRERA Property Intelligence · Palghar

Sunteck MaxxWorld 4, Tivri, Naigaon East

P99000024173 · Tivri · promoter Sunteck Realty Limited

Certificate SignedDue 30 Dec 2025

Delivery & Registration

MahaRERA registrationP99000024173
Registered on23 Jan 2020
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sunteck Realty Limited is the promoter of record on 41 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~74.9% of the estimated project cost incurred as of the last certificate (₹30.45 Cr spent against a ₹40.67 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~74.9% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
Sunteck HillView 11G+2330 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Nclt127 of 20192019Pending

Location, Land & Connectivity

Located at Tivri , Tivri , Andheri, Mumbai Suburban, 401208. Per the filed land record, the plot is bounded to the north by 30 meter Road and Vasai Diwa Railway Line, to the south by Rivulet, to the east by 40 meter wide Road and to the west by 30 meter wide Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sunteck Realty Limited is the promoter on 25 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Sunteck Realty Limited project & its RERA track record →

Other flagged projects by Sunteck Realty Limited

Sunteck Realty Limited
FlaggedMumbai Suburban
Sunteck Realty Limited
FlaggedMumbai Suburban
Sunteck Realty Limited
FlaggedMumbai Suburban
Sunteck Realty Limited
FlaggedMumbai Suburban
Sunteck Realty Limited
FlaggedMumbai Suburban
Sunteck Realty Limited
FlaggedPalghar

Other RERA-registered projects in Vasai East

Samruddhi Ind. Estate
possession by Jul 2026 · Krisha Buildtech LLP
Armaan Crystal Uptown
possession by Aug 2026 · Armaan Housing LLP
Nakshatra Aarambh
possession by Sep 2026 · JSB Shelters LLP
AAI Chandika Hills
possession by Sep 2026 · Shivam Builders & Developers
Dreams Heights Building NO- I
possession by Sep 2026 · Lodha Builders AND Developers
Trinity Oasis
possession by Sep 2026 · Harsh Tirupati Developers LLP

Major developers building in Vasai East

Other RERA-registered projects in Palghar

Sunteck Maxxworld 5, Tivri, Naigaon East
possession by Dec 2026 · Sunteck Realty Limited
Sunteck Oneworld 1, Tivri, Naigaon East
possession by Jun 2027 · Sunteck Realty Limited
Sunteck Oneworld 2, Tivri, Naigaon East
possession by Jun 2027 · Sunteck Realty Limited
Sunteck Oneworld 3, Tivri, Naigaon East
possession by Dec 2026 · Sunteck Realty Limited
Sunteck Oneworld 4, Tivri, Naigaon East
possession by Dec 2026 · Sunteck Realty Limited
Sunteck Oneworld 5, Tivri, Naigaon East
possession by Dec 2026 · Sunteck Realty Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026