MahaRERA Property Intelligence · Thane

Upper Thane - Tiara C

P51700016437 · Bhiwandi · promoter Lodha

Certificate SignedDue 30 Sep 2023

Delivery & Registration

MahaRERA registrationP51700016437
Registered on10 May 2018
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
Tiara C1G+2030 Sep 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Bhiwandi, Mumbai Nashik Highway, Mumbai City, Mumbai City, 421302. Per the filed land record, the plot is bounded to the north by CS no 49by5 pt and 49by3 pt, to the south by CS no 53 pt, to the east by CS no 50 pt and to the west by CS no 52by1 pt. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~21 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park21 km
Andheri MIDC / SEEPZ23 km
Chhatrapati Shivaji Int'l Airport26 km
Bandra Kurla Complex (BKC)28 km
Lower Parel / Worli business district36 km
Nariman Point / Fort43 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 171 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane

Other RERA-registered projects in Bhiwandi

Neelkanth Sadan
possession by Jul 2026 · Shreeji Enterprises
Hill Spring
possession by Aug 2026 · Asha Infratech
Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

Upper Thane - Tiara D
declared completion Mar 2024 · Lodha Developers Limited
Upper Thane - Tiara E, F
declared completion Jun 2025 · Lodha Developers Limited
Upper Thane - Tiara G
possession by Jan 2028 · Lodha Developers Limited
Upper Thane - Tiara H
declared completion Nov 2025 · Lodha Developers Limited
Upper Thane-Tiara H
possession by Jul 2027 · Lodha Developers Limited
Upper Thane - Tiara I
declared completion Mar 2024 · Lodha Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026