VISHWAS CHS

Mumbai City · Siroya Yug Realtors

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800006461

Delivery and registration

When is the project declared for completion?

VISHWAS CHS is registered with MahaRERA as P51800006461 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800006461
Registered on14 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VISHWAS CHS record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Siroya Yug Realtors is the promoter of record on 8 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VISHWAS CHS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
VISHWAS CHS1G+15-

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for VISHWAS CHS, with orders passed in 4 of them.

4complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005724113/12/2018Jayaben V. Pasad vs Siroya Yug Realtorsorder passed
CC00600000005724912/12/2018Ramasubramanian R. Nadar vs Siroya Yug Realtorsorder passed
CC00600000005806511/03/2019Pradip Parab vs Siroya Yug Realtorsorder passed
CC00600000005722713/12/2018R. Ganeshan vs Siroya Yug Realtorsorder passed

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400071. Per the filed land record, the plot is bounded to the north by SS III ROAD NO 11, to the south by PLOT BEARING CTS NO 1492 1493, to the east by PLOT BEARING CTS NO 1472 and to the west by PLOT BEARING CTS NO 1470. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport6 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Lower Parel / Worli business district10 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chembur

Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited
Laxmina Krishna Niwas
possession by Oct 2026 · Laxmina Argentum Realties Private Lim
Safal SAI AND Safal Sainath
possession by Oct 2026 · Mangalnath Developers PVT LTD

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Vishwas Niketan By Viiaan
possession by Dec 2026 · Somani Buildtech LLP
Vishwasangam
possession by Dec 2026 · Vishwashakti Cooperative Housing Society
Vision Heights Wing A
declared completion Dec 2025 · Fiona Realty Private Limited
Vision Heights Wing B
declared completion Dec 2025 · Fiona Realty Private Limited
Vision Heights Wing C
declared completion Jun 2025 · Fiona Realty Private Limited
Vista
declared completion Dec 2025 · Elite Housing LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026