WINDSOR TOWER B
BHAYANDER WEST · GRANDBUILD LAND DEVELOPERS LLP
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 02 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Mar 2032
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 02 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700081067
Delivery and registration
When is the project declared for completion?
WINDSOR TOWER B is registered with MahaRERA as P51700081067 and the promoter has declared completion for 31 Mar 2032.
31 Mar 2032
declared completion
66months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 02 Jul 2026
| MahaRERA registration | P51700081067 |
| Registered on | 11 Dec 2025 |
| Promoter-declared completion | 31 Mar 2032 |
| Current status | Certificate Signed |
| Against today | 66 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for WINDSOR TOWER B record 2 quarterly progress reports since registration.
2quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 02 Jul 2026
- Suspended / abeyance — the registration is suspended or in abeyance.
- Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Grandbuild Land Developers is the promoter of record on 4 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
4projects
registered with MahaRERA
4flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 02 Jul 2026
Construction
How much construction cost has been reported?
In WINDSOR TOWER B, ₹5.38 Cr of a declared ₹121.32 Cr estimated project cost is reported as incurred, about 4.4%, as at the last certified filing with MahaRERA.
4.4%
₹5.38 Cr
of ₹121.32 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 02 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for WINDSOR TOWER B in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 20 September 2026
What the filings record, home by home
Read from MahaRERA on 20 September 2026
No home in WINDSOR TOWER B carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 264 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 10,081 a sq ft typical, over Rs 9,623 to Rs 12,085.
A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.
The Reckoner Record lists all 264 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+38 and 264 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| WINDSOR TOWER B | 1 | G+38 | 264 | - |
Unit mix on the filing: 257 residential and 7 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at BHAYANDER WEST , MAHESHWARI BHAVAN ROAD , Mumbai City, Mumbai City, 400101. Per the filed land record, the plot is bounded to the north by KHADI, to the south by 18 MTR D P ROAD, to the east by WINDERMERE and to the west by RADHOSWAMI SATASANG. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 18 km |
| Powai / Hiranandani business park | 20 km |
| Chhatrapati Shivaji Int'l Airport | 22 km |
| Bandra Kurla Complex (BKC) | 25 km |
| Lower Parel / Worli business district | 33 km |
| Nariman Point / Fort | 41 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.