Mumbai/Project record

MahaRERA · the public record

YASH HEIGHTS

GOVANDI STATION · PARAS SUNDERJI DEDHIA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800015300

Delivery and registration

When is the project declared for completion?

YASH HEIGHTS is registered with MahaRERA as P51800015300 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800015300
Registered on15 Feb 2018
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for YASH HEIGHTS record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Paras Sunderji Dedhia is the promoter of record on 2 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for YASH HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
YASH HEIGHTS1G+1231 Dec 2020

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for YASH HEIGHTS, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000017182117/12/2019KRISHNAKUMAR V. vs YASH BUILDERSorder passed

Location, Land & Connectivity

Located at GOVANDI STATION, GOVANDI STATION ROAD, Kurla, Mumbai Suburban, 400088. Per the filed land record, the plot is bounded to the north by SURVEY NO 92 H NO 2, to the south by SURVEY NO 92 H NO 10, to the east by SURVEY NO 92 HNO 6 and to the west by PUBLIC ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)7 km
Chhatrapati Shivaji Int'l Airport8 km
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Lower Parel / Worli business district12 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Paras Sunderji Dedhia is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Paras Sunderji Dedhia

Paras Sunderji Dedhia
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Deonar

Surve Tower
possession by Dec 2026 · Meena Vikas Raikar
Gagan Giri Co-Operative Housing Society Limited
Not filing quarterly progress reports · possession by Dec 2026 · Mishal Construction Private Limited
Akshar Amar Mansion
possession by Mar 2027 · Akshar Properties
Anuvidnyan Nagar Co-Op. Housing Society Ltd
possession by Jun 2027 · Makwise Homes LLP
Purva Clermont Wing A
possession by Jun 2027 · Puravankara Limited
Purva Clermont Wing B
possession by Jun 2027 · Puravankara Limited

Major developers building in Deonar

Other RERA-registered projects in Mumbai Suburban

Yash Mayuri
possession by Dec 2030 · Yash Construction Co
Yash Pratik
possession by Dec 2028 · Yash Infomedia & Estate Private Limi
Yash Residency
possession by Jan 2030 · Not Available
Yashashree
possession by Dec 2028 · Trupti Buildcon LLP
Yashomati Chsl
declared completion Apr 2026 · Samrat Enterprise
Yashraj Heights
declared completion Nov 2023 · Yashraj Corporation

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026