Pune/Project record

MahaRERA · the public record

30 DRIVE

PUNE · Duville Estates Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

06 May 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

06 May 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100032106

Delivery and registration

When is the project declared for completion?

30 DRIVE is registered with MahaRERA as P52100032106 and the promoter has declared completion for 06 May 2024.

06 May 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100032106
Registered on14 Dec 2021
Promoter-declared completion06 May 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 30 DRIVE record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Duville Estates is the promoter of record on 8 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for 30 DRIVE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
30 DRIVE1G+1030 Nov 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 5 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Court Of Civil Judge Senior Division Pune1774/20152015Closed
Court Of Civil Judge Senior Division Pune226/20152015Ongoing
Court Of Civil Judge Senior Division Pune597/20152015Ongoing
Pune Civil Court48/20162016Pending
Court Of Civil Judge Senior Division Pune2262015Ongoing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered06 May 2024During the covid-19 pandemic period the works in the said Project has got delayed due to inadequate manpower and difficulty in re-mobilisation of resources. As a result of which, w

Location, Land & Connectivity

Located at PUNE, GHORPADI, Pune City, Pune, 411001. Per the filed land record, the plot is bounded to the north by 30 MTR ROAD, to the south by NYATI EMPERIA, to the east by NYATI ELYSIA and to the west by BAIG VASTI. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Duville Estates Private Limited is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Duville Estates Private Limited project & its RERA track record →

Other flagged projects by Duville Estates Private Limited

Duville Estates Private Limited
FlaggedPune
Duville Estates Private Limited
FlaggedPune

Other RERA-registered projects in Ghorpadi

Royal Glen
possession by Sep 2026 · Stargaze Buildcon
Ganga Bhagyoday E Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Ganga Bhagyoday F Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Boulevard Tower A2
possession by Dec 2026 · Bramhacorp Limited
Casaverde
possession by Dec 2026 · Skyboat Infrastructure Unit 1 LLP
Eternia Phase 2
possession by Dec 2026 · Venturespro Projects LLP

Major developers building in Ghorpadi

Other RERA-registered projects in Pune

31 Palma Drive Phase 1
possession by Jun 2029 · Sagar Construction Company
31 Palma Drive Phase 2
possession by Dec 2030 · Sagar Construction Company
31 Shivalay
declared completion Apr 2025 · Mahendra Dharamchand Phulfagar
32 Pinewood Drive -Phase2
declared completion Dec 2025 · S S Properties
33 Central Avenue Wing F-1
possession by Dec 2029 · Eisha Properties Unit 5
33 Central Avenue Wing F-3
possession by Dec 2028 · Eisha Properties Unit 5

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026