32 Pinewood Drive -Phase2

Hinjewadi Phase 3 · S S Properties

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

1units filed as unsoldInventory · 18 September 2026
30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100033337

Delivery and registration

When is the project declared for completion?

32 Pinewood Drive -Phase2 is registered with MahaRERA as P52100033337 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100033337
Registered on16 Feb 2022
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 32 Pinewood Drive -Phase2 record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 168 homes carry one, and 1 of the 169 are recorded unsold.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In 32 Pinewood Drive -Phase2, 0 of the 1 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 1 home — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
C1G+13-
D1G+13-
Commercial Building1G+0-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court Of Judicature At Bombay121922022Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2025We are submitting this explanatory note to request an extension for the completion of Wing D under the 32 Pinewood Drive - Phase 2 project. Grounds for Delay 1. Completion of Win

Location, Land & Connectivity

Located at Hinjewadi Phase 3, Bhoirwadi road, Haveli, Pune, 411057. Per the filed land record, the plot is bounded to the north by Proposed 15 m Wide road, to the south by Open space, to the east by 12 M Wide Internal Road and to the west by Survey no 31 Part. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~97 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park97 km
Baner–Balewadi belt102 km
Pune Int'l Airport (Lohegaon)111 km
Pune Junction / city centre111 km
Kharadi / EON IT Park115 km
Magarpatta / Hadapsar IT116 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

S S Properties is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Wakad

ANP Memento
possession by Sep 2026 · Five Star Construction Company
Manor Crystal
possession by Sep 2026 · Oxford Infra Group
Park59
possession by Sep 2026 · Shiv Developers
Sensorium, Phase VI
possession by Sep 2026 · Joyville Shapoorji Housing Private Limit
Sonchandr Residency
possession by Sep 2026 · Chandan Ramdas Kate
Spring Residency
possession by Sep 2026 · Pritam Ashok Kachi

Major developers building in Wakad

Other RERA-registered projects in Pune

33 Central Avenue Wing F-1
possession by Dec 2029 · Eisha Properties Unit 5
33 Central Avenue Wing F-3
possession by Dec 2028 · Eisha Properties Unit 5
34 Western Pavillion
declared completion Sep 2026 · Blue Pearl Promoters AND Developers
37 Grandstand
possession by May 2027 · Space Builders AND Developers
38 Daffodils
possession by Jul 2028 · Blue Pearl Realty
38 Park Majestique Phase IV
declared completion Jun 2025 · Majestique Promoters AOP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.