PARK TITAN PHASE III

MARUNJI · PRIDE PURPLE INFRASTRUCTURE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100049631

Delivery and registration

When is the project declared for completion?

PARK TITAN PHASE III is registered with MahaRERA as P52100049631 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

9months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100049631
Registered on22 Feb 2023
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today9 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PARK TITAN PHASE III record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Pride Purple Infrastructure is the promoter of record on 23 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

23projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PARK TITAN PHASE III in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
TOWER 61G+24-
TOWER 11G+24-
TOWER 71G+24-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Shivajai Nagar Civil Judge Senior Division21872019Pending For Exh Five Argument
Shivajai Nagar Civil Judge Senior Division1872020Pending For Exh Five Argument
Civil Court Senior Division, Pune21872019Ongoing

Location, Land & Connectivity

Located at MARUNJI, MARUNJI, Pune City, Pune, 411057. Per the filed land record, the plot is bounded to the north by S NO 39, to the south by PLOT NO 6 AND 5, to the east by PLOT NO 3 and to the west by PART OF S NO 44. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pride Purple Infrastructure is the promoter on 10 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Pride Purple Infrastructure project & its RERA track record →

Other flagged projects by Pride Purple Infrastructure

Pride Purple Infrastructure
FlaggedPune
Pride Purple Infrastructure
FlaggedPune
Pride Purple Infrastructure
FlaggedPune
Pride Purple Infrastructure
FlaggedPune
Pride Purple Infrastructure
FlaggedPune
Pride Purple Infrastructure
FlaggedPune

Other RERA-registered projects in Wakad

ANP Memento
possession by Sep 2026 · Five Star Construction Company
Manor Crystal
possession by Sep 2026 · Oxford Infra Group
Park59
possession by Sep 2026 · Shiv Developers
Sensorium, Phase VI
possession by Sep 2026 · Joyville Shapoorji Housing Private Limit
Sonchandr Residency
possession by Sep 2026 · Chandan Ramdas Kate
Spring Residency
possession by Sep 2026 · Pritam Ashok Kachi

Major developers building in Wakad

Other RERA-registered projects in Pune

Park Titan Phase IV
possession by Mar 2028 · Pride Purple Infrastructure
Park Titan Phase V
possession by Aug 2029 · Pride Purple Infrastructure
Park View Phase 2
declared completion Dec 2024 · Mantra Earth LLP
Park Vista Phase 3
declared completion Nov 2024 · Prime Buildcon
Park West
possession by Dec 2028 · Hapse Spaces
Park West
possession by Dec 2027 · Infinity Buildcon

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026