Pune/Project record

MahaRERA · the public record

Godrej Evergreen Square

Rajiv Gandhi Infotech Park Phase III Industrial Area · Godrej Projects Development Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

503units filed as unsoldInventory · 20 September 2026
31 Oct 2030declared completionMahaRERA registration · read 12 Jul 2026
2,476registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Oct 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100078240

Delivery and registration

When is the project declared for completion?

Godrej Evergreen Square is registered with MahaRERA as P52100078240 and the promoter has declared completion for 31 Oct 2030.

31 Oct 2030

declared completion

49months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100078240
Registered on29 Nov 2024
Promoter-declared completion31 Oct 2030
Current statusCertificate Signed
Against today49 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Godrej Evergreen Square record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Godrej Properties is the promoter of record on 62 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

62projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Godrej Evergreen Square, ₹100.51 Cr of a declared ₹1176.76 Cr estimated project cost is reported as incurred, about 8.5%, as at the last certified filing with MahaRERA.

8.5%

₹100.51 Cr

of ₹1176.76 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Godrej Evergreen Square, 1,973 of 2,476 homes filed with MahaRERA are recorded as sold or booked (1,746 with registered agreements and 227 booked), about 80%, and 503 remain available.

80%sold

1,973 of 2,476 homes

₹1523.68 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹473.84 Cr (about 31%) is recorded as collected and ₹1049.84 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 1973 registered agreements, the effective carpet rate is ₹11,471/sqft, with eight in ten falling between ₹10,698 and ₹13,131 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 1973 homes carry one, and 503 of the 2476 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
GESRP1071624 sqftRs 68.39 lakh typical, over Rs 64.05 lakh to Rs 3.1942 cr760 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Godrej Evergreen Square, 490 of the 503 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 502 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+36 and 2476 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Retail Shop1G+696-
Tower 21G+36378-
Tower 31G+36378-
Tower 41G+36250-
Tower 51G+36264-
Tower 61G+35260-
Tower 71G+34252-
Tower 81G+35326-
Amenity Building1G+322-
Tower 11G+36250-

Unit mix on the filing: 2358 residential and 118 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for Godrej Evergreen Square, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250155512/05/2025Shailendra Dilip Raste vs Godrej Projects Development Limitedorder passed
CC1250202721/06/2025Amol Sambhaji Vilegave vs Godrej Projects Development Limitedorder passed
CC1260115603/03/2026Meghana Singh vs Godrej Projects Development Limitedorder passed
CC1260120806/03/2026Meenakshi Dagar vs Godrej Projects Development Limitedorder passed
CC1260230719/04/2026Jeetendra Singh vs Godrej Projects Development Limitedorder passed

Location, Land & Connectivity

Located at Rajiv Gandhi Infotech Park Phase III Industrial Area, Hinjewadi Phase 3, Kurla, Mumbai Suburban, 411057. Per the filed land record, the plot is bounded to the north by 45M Wide MIDC Road, to the south by MIDC Boundary, to the east by 60M Wide MIDC Road and to the west by Plot No R-1-2-B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~48 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park48 km
Baner–Balewadi belt51 km
Pune Junction / city centre60 km
Magarpatta / Hadapsar IT65 km
Pune Int'l Airport (Lohegaon)66 km
Kharadi / EON IT Park67 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Godrej Projects Development Limited is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Godrej Projects Development Limited project & its RERA track record →

Other RERA-registered projects in Wakad

ANP Memento
possession by Sep 2026 · Five Star Construction Company
Manor Crystal
possession by Sep 2026 · Oxford Infra Group
Park59
possession by Sep 2026 · Shiv Developers
Sensorium, Phase VI
possession by Sep 2026 · Joyville Shapoorji Housing Private Limit
Sonchandr Residency
possession by Sep 2026 · Chandan Ramdas Kate
Spring Residency
possession by Sep 2026 · Pritam Ashok Kachi

Major developers building in Wakad

Other RERA-registered projects in Pune

Godrej Green Cove
declared completion Jun 2026 · Mahalunge Township Developers Private Li
Godrej Green Vistas
declared completion May 2026 · Mahalunge Township Developers Private Li
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Godrej Hill Retreat
possession by Dec 2026 · Mahalunge Township Developers Private Li
Godrej Hill Retreat 2
possession by Mar 2027 · Mahalunge Township Developers Private Li
Godrej Hillside 2
declared completion Oct 2024 · Mahalunge Township Developers LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026