Aishwarya Square

KOthrud · MADKAR CONSTRUCTIONS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jul 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jul 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100051446

Delivery and registration

When is the project declared for completion?

Aishwarya Square is registered with MahaRERA as P52100051446 and the promoter has declared completion for 30 Jul 2025.

30 Jul 2025

declared completion

14months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100051446
Registered on14 Jun 2023
Promoter-declared completion30 Jul 2025
Current statusCertificate Signed
Against todayabout 14 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Aishwarya Square record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Madkar Constructions is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Aishwarya Square in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Aishwarya Square1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jul 2025At the inception of the project, we had estimated that the project would be completed by July 31, 2024. However, after starting the excavation, we encountered substantial hard rock

Location, Land & Connectivity

Located at KOthrud, Kothrud, Pune City, Pune, 411038. Per the filed land record, the plot is bounded to the north by By Pune-Paud road, to the south by By Plot no 3 of Bhagya-Chintamani Society Layout, to the east by By 25 feet Wide road of Layout and to the west by By Plot no 3 of Bhagya-Chintamani Society Layout. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Madkar Constructions Private Limited is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Madkar Constructions Private Limited

Madkar Constructions Private Limited
FlaggedPune
Madkar Constructions Private Limited
FlaggedPune

Other RERA-registered projects in Kothrud

Arunali
possession by Sep 2026 · Badhekar Properties
Guruvaibhav CO-Op.housing Society Limited
possession by Sep 2026 · Shreepad Associates
Prathamesh Co-Op Housing Soc
possession by Sep 2026 · Joshi Associates
State Bank OF India Snehdeep Chsl
possession by Sep 2026 · Kotibhaskar Infrastructures &develop
Vaibhavshree AND Indira Priyadarshani
possession by Sep 2026 · Pride Properties & Infrastructure
Yakshanagari CO Operative Housing Society LTD
possession by Sep 2026 · VSA Intezine LLP

Major developers building in Kothrud

Other RERA-registered projects in Pune

Aishwarya Township
possession by Feb 2027 · Not Available
Aishwaryam
declared completion Jun 2023 · Aditya Associates
Aishwaryam Anand
possession by Dec 2029 · Sai Essen Developers
Aishwaryam Courtyard Gold
possession by Dec 2028 · SAI Essen Properties
Aishwaryam Future
possession by Oct 2027 · SAI Swaraj Realtors
Aishwaryam Hamara Abhimaan
declared completion Dec 2024 · SAI Essen Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026