MahaRERA Property Intelligence · Pune

ANANDTARA WHITEFIELD RESIDENCIES PHASE-II

P52100018257 · LONKAR VASTI · promoter Anandtara Infrastructure

Certificate SignedDue 28 Feb 2021

Delivery & Registration

MahaRERA registrationP52100018257
Registered on22 Oct 2018
Promoter-declared completion28 Feb 2021
Current statusCertificate Signed
Against todayabout 65 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Anandtara Infrastructure is the promoter of record on 8 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
A BUILDING1G+1130 Aug 2020
B BUILDING1G+1130 Aug 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
28 Feb 202128 Feb 2022We were required to handover area under road widening and claim FSI as compensation to the same. However, the process has taken longer than the usually estimated time. Hence out of

Location, Land & Connectivity

Located at LONKAR VASTI, KESHAVNAGAR, Pune City, Pune, 411036. Per the filed land record, the plot is bounded to the north by SURVEY NO 32 PART, to the south by SURVEY NO 32 PART, to the east by BY 18 MTRS WIDE ROAD SURVEY NO 32 PART and to the west by SURVEY NO 32 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Anandtara Infrastructure is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Anandtara Infrastructure

Anandtara Infrastructure
FlaggedPune
Anandtara Infrastructure
FlaggedPune
Anandtara Infrastructure
FlaggedPune
Anandtara Infrastructure
FlaggedPune

Other RERA-registered projects in Mundhwa

Moonstone
possession by Aug 2026 · Swamiji Developers
Matoshree Pride
Not filing quarterly progress reports · possession by Aug 2026 · Devidas Suresh Bhat
Shubh Evan C1 Wing
possession by Aug 2026 · Kalash Enterprises
Casa Elanza
possession by Sep 2026 · Parmaz Green Realty LLP
Platinum Capital Office - Phase I
possession by Sep 2026 · A Advani Properties LLP
The Golden Bell
Not filing quarterly progress reports · possession by Dec 2026 · Panchshil Hotels Pvt Ltd

Major developers building in Mundhwa

Other RERA-registered projects in Pune

Anandtaras Haritara
declared completion Dec 2019 · Anandtara Properties
Anandvan
declared completion Dec 2023 · Anil Wamanrao Shinde
Anandvan
declared completion Jun 2026 · M/s Skyline Ventures
Anandwan
declared completion Jun 2024 · Viraj Properties
Anandwan Apartment
declared completion Dec 2025 · Rudransh Infra
Anant
declared completion Dec 2022 · Ranjekar Realty LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026