MahaRERA · the public record
Antheia C3
Pimpri · Mahindra Lifespace Developers limited
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Mar 2023
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100016619
Delivery and registration
When is the project declared for completion?
Antheia C3 is registered with MahaRERA as P52100016619 and the promoter has declared completion for 30 Mar 2023.
30 Mar 2023
declared completion
42months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100016619 |
| Registered on | 25 May 2018 |
| Promoter-declared completion | 30 Mar 2023 |
| Current status | Certificate Signed |
| Against today | about 42 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Antheia C3 record 20 quarterly progress reports since registration.
20quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Antheia C3 in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Antheia C3 | 1 | G+25 | 30 Mar 2022 |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Legal & Litigation
The promoter has declared 2 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Court Of Civil Judge Senior Division Pune | 926 | 2015 | Pending |
| High Court Mumbai | 24692 | 2016 | Pending |
Location, Land & Connectivity
Located at Pimpri, Nehru nagar Rd, Ward GSouth, Mumbai City, 411018. Per the filed land record, the plot is bounded to the north by Building C2 of Antheia, to the south by Building D4 of Antheia, to the east by CTS No 6019 and 6020 part 3 and 6017 part 3 part and to the west by Building A3 of Antheia. These are the boundaries as recorded in the filed land record.