DIAMOND RESIDENCY

NEHRU NAGAR · ACCSPEE INDIA PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100011188

Delivery and registration

When is the project declared for completion?

DIAMOND RESIDENCY is registered with MahaRERA as P52100011188 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100011188
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DIAMOND RESIDENCY record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DIAMOND RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
DIAMOND RESIDENCY1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2021Due to Financial Crisis and Contractor Default, the Building could not be completed. We have not sold any flats / received any kind of Advances

Location, Land & Connectivity

Located at NEHRU NAGAR, SANTOSHI MATA CHOWK, Bhiwandi, Thane, 411018. Per the filed land record, the plot is bounded to the north by SURAJ VERMA AND SHIV ASSOCIATES, to the south by SONIGARA BUILDERS, to the east by 30 FOOT WIDE ROAD and to the west by KESHAV BHANUSHALI. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~102 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park102 km
Baner–Balewadi belt107 km
Pune Junction / city centre118 km
Pune Int'l Airport (Lohegaon)119 km
Kharadi / EON IT Park123 km
Magarpatta / Hadapsar IT123 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pimpri

Stella Apex
possession by Oct 2026 · Vastuspace Realty Promoters AND Develope
Dharampal Corporate Avenue
possession by Dec 2026 · Surender Dharampal Agarwal
Skylish Vaastuu
possession by May 2027 · Skylish Bluediamond Innfrracon
Santoshi Mata Complex
possession by Aug 2027 · Njhb Properties
Bramha Sky Uzuri Phase 2
possession by Dec 2027 · Bramha Leisures PVT LTD
Kohinoor World Tower Phase II
possession by Dec 2027 · Godiva Properties Private Limited

Major developers building in Pimpri

Other RERA-registered projects in Pune

Diamond Rockk
declared completion Nov 2020 · Swastik Developers
Digambar Heights
declared completion Sep 2022 · Maruti Shivaji Kalbhor
Dikshit Baug Apartment C
declared completion Dec 2020 · Hindustan Builders
Dinesh Sopan Shedge And Rahul Arjun Mane
declared completion Dec 2021 · M/s Dinesh Sopan Shedge & Rahul Arjun Ma
Dinkar Apartment
declared completion Jun 2026 · Siddhhidata Realtors
Dinkar Apartments
possession by Nov 2028 · Paranjpe Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026