MahaRERA Property Intelligence · Pune
P52100002620 · Tathawade · promoter Shri Siddhivinayak Developers
| MahaRERA registration | P52100002620 |
| Registered on | 02 Aug 2017 |
| Promoter-declared completion | 30 Apr 2023 |
| Current status | Certificate Signed |
| Against today | about 39 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| F | 1 | G+14 | 31 Dec 2023 |
| G | 1 | G+14 | 31 Dec 2023 |
| H | 1 | G+14 | 31 Dec 2023 |
| I | 1 | G+12 | 31 Dec 2023 |
18 complaints are on the MahaRERA record for this project, with orders passed in 17. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000096252 | 15/11/2021 | nilesh madhukar ghorpade vs Shree Anuj Umesh GOEL (GANGA AMBER) | order passed |
| CC005000000106417 | 30/12/2021 | MR. MILIND SITARAM SHETE vs SHRI SIDDHIVINAYAK DEVELOPERS | order passed |
| CC005000000106681 | 23/02/2022 | ANITA MALLIKARJUN BIRAJDAR vs Shri Siddhivinayak Developers | order passed |
| CC005000000106856 | 29/03/2022 | 1. Toufik Najirahamed Samalewale 2. Mohsina Toufik Samalewale vs 1. Shri. Siddhivinayak Developers 2. Meenamani Ganga Builder LLP 3. Ecostar Properties LLP | order passed |
| CC005000000116886 | 03/04/2022 | SHRUTI ANIL MALUSHTE vs SHRI SIDDHIVINAYAK DEVELOPERS | order passed |
| CC005000000127105 | 12/05/2022 | PRASHANT SHRIRAM PETKAR vs M/s. Siddhivinayak Developers | order passed |
| CC005000000238546 | 04/04/2023 | DINESH BHIKA LOHAR vs SHRI SIDDHIVINAYAK DEVELOPERS | order passed |
| CC005000000208287 | 17/03/2023 | Ujawala Dadabhau Gawade vs Anuj Goel | order passed |
| CC005000000238545 | 04/04/2023 | CHETAN KASHINATH PAWAR vs SHRI SIDDHIVINAYAK DEVELOPERS | order passed |
| CC005000000238547 | 28/04/2023 | MRS. ROHINI VILASRAO PAWAR vs SHRI SIDDHIVINAYAK DEVELOPERS | order passed |
| CC005000000238548 | 21/04/2023 | SHRIDHAR BAJIRAO DHANE vs SHRI SIDDHIVINAYAK DEVELOPERS | order passed |
| CC005000000310451 | 31/03/2024 | DINESH DEVIDASRAO DEOSARKAR vs SHRI SIDDHIVINAYAK DEVELOPERS | order passed |
| CC005000000371028 | 03/06/2024 | Anuj Goel vs Amol Sharad Aher | order passed |
| CC005000000411066 | 28/06/2024 | Anuj Goel vs Juveriya Desai | order passed |
| CC005000000411076 | 28/06/2024 | Anuj Goel vs Pravin Nikam | order passed |
| CC005000000441128 | 13/06/2024 | AMOL SHARAD AHER vs Shri Siddhivinayak Developer/ Anuj Goel | order passed |
| CC005000000471393 | 28/07/2024 | Mayur H Shah vs Goel Ganga Developments | order passed |
| CC12500112 | 12/01/2025 | AMOL BHAUSAHEB BAGUL vs SHRI SIDDHIVINAYAK DEVELOPERS | pending / no order on file |
The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Apr 2023 | 30 Sep 2022 | We have registered our project on 02/08/2017 and proposed completion date was 30/06/2022. According to that authority had granted our project and issued MahaRERA Registration Certi |
| 30 Apr 2023 | 30 Apr 2023 | Due to Covid 19 and unavailability of resources. |
Located at Tathawade, amber street, Pune City, Pune, 411033. Per the filed land record, the plot is bounded to the north by SNO 60 PART, to the south by SNO 59 PART, to the east by SNO 60 PART and to the west by SNO 59 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 3 km |
| Baner–Balewadi belt | 7 km |
| Pune Junction / city centre | 16 km |
| Pune Int'l Airport (Lohegaon) | 18 km |
| Kharadi / EON IT Park | 21 km |
| Magarpatta / Hadapsar IT | 22 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in GANGA AMBER PH I?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Shri Siddhivinayak Developers is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026