iOS Tathawade

Tathawade · Linux Group

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

41units filed as unsoldInventory · 17 September 2026
30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
165registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100027952

Delivery and registration

When is the project declared for completion?

iOS Tathawade is registered with MahaRERA as P52100027952 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100027952
Registered on21 Jan 2021
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for iOS Tathawade record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Linux Group is the promoter of record on 6 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In iOS Tathawade, ₹42.00 Cr of a declared ₹42.00 Cr estimated project cost is reported as incurred, about 100.0%, as at the last certified filing with MahaRERA.

100.0%

₹42.00 Cr

of ₹42.00 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In iOS Tathawade, 124 of 165 homes filed with MahaRERA are recorded as sold or booked, about 75%, and 41 remain available.

75%sold

124 of 165 homes

₹65.22 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹56.86 Cr (about 87%) is recorded as collected and ₹8.37 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 124 registered agreements, the effective carpet rate is ₹6,766/sqft, with eight in ten falling between ₹5,995 and ₹7,419 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 124 homes carry one, and 41 of the 165 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
209718 sqftRs 6,593 a sq ft typical, over Rs 5,744 to Rs 7,45964 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In iOS Tathawade, 18 of the 41 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 40 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16 and 165 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
iOS Tathawade1G+16140-
iOS Complex1G+325-

Unit mix on the filing: 140 residential and 25 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

48 complaints are on the MahaRERA record for iOS Tathawade, with orders passed in 47 of them.

48complaints

47with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000025882304/08/2024Mangesh Tukaram Surkar vs Neerajorder passed
CC00500000028999711/01/2024ASHISH KASHINATH THAKRE vs ios Tathawadeorder passed
CC00500000047130304/08/2024Nitin Karnish Agarwal vs Sanjay Singh/ Linux Grouporder passed
CC00500000047145204/08/2024Pankaj Prabhakar Khairnar vs Linux Grouporder passed
CC00500000047154815/08/2024Vivek Ramrao Labhade vs Linux Grouporder passed
CC1240036507/10/2024SHIRISH VITTHALRAO DESHMUKH vs Linux Grouporder passed
CC1240005606/09/2024Sumit Shashikant Patki vs Sumit Shashikant Patki (For Compensation)order passed
CC1240032904/10/2024Mayur Rameshrao Bijwe vs Linux Grouporder passed
CC1240034105/10/2024Swarup Sanjay Suryawanshi vs Linux Grouporder passed
CC1240034305/10/2024SURAJ ASHOK BILONE vs Linux Grouporder passed
CC1240037007/10/2024Bhushan Narendra Teli vs Linux Grouporder passed
CC1240034405/10/2024Nilesh Madhav Kokane vs Linux Grouporder passed
CC1260118004/03/2026Nitin Harishchandra Nawale vs Linux Grouporder passed
CC1240060728/10/2024Diptish Deepak Kolekar vs Linux Grouporder passed
CC1240037408/10/2024anil raman lala bankey vs Linux Grouporder passed
CC1240041715/10/2024Rahul Ankush Bangar vs Linux Grouporder passed
CC1240047620/10/2024shivkailash kaurbhan agarwal vs Linux Grouporder passed
CC1240121424/12/2024ASHISH KASHINATH THAKRE vs Linux Grouporder passed
CC1250003604/01/2025Somnath Eknath Nagare vs Linux Grouporder passed
CC1250007508/01/2025LALIT MOHAN BADGUJAR vs Linux Grouporder passed
CC1250009209/01/2025VIKAS BHAGOJI BANDRE vs vikas bandreorder passed
CC1260024414/01/2026Tushar Jadhav vs Linux Grouporder passed
CC1260097623/02/2026Uzma Ashraf Lambe vs Linux Grouporder passed
CC1260093520/02/2026Akhilesh Manohar Kshirsagar vs Linux Grouporder passed
CC1260097523/02/2026Rahul Jagtap vs Linux Grouporder passed
CC1260099223/02/2026Ashish Powar vs Linux Grouporder passed
CC1260099323/02/2026Arjun Paithane vs Linux Grouporder passed
CC1260099423/02/2026Pankaj Rakibe vs Linux Grouporder passed
CC1260099724/02/2026Snehal Bhavsar vs Linux Grouporder passed
CC1260100424/02/2026Trunal Zambare vs Linux Grouporder passed
CC1260115703/03/2026Shree Kulkarni vs Linux Grouporder passed
CC1260115803/03/2026Aamir Ashraf Lambey vs Linux Grouporder passed
CC1260115903/03/2026Arunabh Tripathi vs Linux Grouporder passed
CC1260116003/03/2026SHUBHAM NERKAR vs Linux Grouporder passed
CC1260116103/03/2026Akash Malpani vs Linux Grouporder passed
CC1260116603/03/2026Ajit Gangathade vs Linux Grouporder passed
CC1260116903/03/2026Tanaji Suryavanshi vs Linux Grouporder passed
CC1260117003/03/2026Alpana Godbole vs Linux Grouporder passed
CC1260117103/03/2026Somnath Eknath Nagare vs Linux Grouporder passed
CC1260117303/03/2026Chetan Sonawane vs Linux Grouporder passed
CC1260117503/03/2026Pooja Lavhale vs Linux Grouporder passed
CC1260147216/03/2026Manoj Navghare vs Linux Grouporder passed
CC1260147316/03/2026Ritesh Jaiswal vs Linux Grouporder passed
CC1260147617/03/2026Deepak Shinde vs Linux Grouporder passed
CC1260147717/03/2026Nikhil Ghawade vs Linux Grouporder passed
CC1260147817/03/2026Swati Kumari vs Linux Grouporder passed
CC1260275811/05/2026Vishakha Patil vs Linux Grouppending / no order on file
CC1260307824/05/2026LALIT MOHAN BADGUJAR vs Linux Grouporder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2024The reasons for Project Extension Application are e.g., financial crunch, market conditions, government Certificates like OCC, Fire NOC, Slow work speed because of heavy Rain like

Location, Land & Connectivity

Located at Tathawade, Jeevan nagar, Haveli, Pune, 411033. Per the filed land record, the plot is bounded to the north by Survey 150 part, to the south by survey 150 part, to the east by Survey 149 and to the west by Survey 156. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park4 km
Baner–Balewadi belt8 km
Pune Junction / city centre17 km
Pune Int'l Airport (Lohegaon)19 km
Kharadi / EON IT Park22 km
Magarpatta / Hadapsar IT23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Linux Group is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Linux Group

Other RERA-registered projects in Punawale

Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE
7 Plumeria Drive- Phase 3
possession by Sep 2026 · B A Consulting
Austin Arena
possession by Sep 2026 · Austin Real Infra LLP
Shree Heritage
possession by Sep 2026 · Bhakti Venkateshwara Developers
Silveroak C1
Deregistered by MahaRERA · possession by Sep 2026 · SAI Samarttha Properties
Vivanta Next
possession by Sep 2026 · Shree Sonigara Punamiya Developers

Major developers building in Punawale

Other RERA-registered projects in Pune

Iqra Residency
declared completion Jul 2024 · Liyaqat Mohd Muslim ALI
IRA
possession by Sep 2027 · Envirant Developers Private Limited
IRA C Building Phase 2
declared completion Dec 2017 · M/S Majestique Mantra Incorporation
Ira Enclave
declared completion Dec 2024 · P G Developers
IRA Icon
possession by Sep 2026 · Tirupati Associates
Iravati
declared completion Jun 2026 · R B Ventures AND Redevelopment Private L

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026