Pune/Project record

MahaRERA · the public record

JM BLISS

Eiffel City · PRITAM JAWAHAR MUTHA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100001273

Delivery and registration

When is the project declared for completion?

JM BLISS is registered with MahaRERA as P52100001273 and the promoter has declared completion for 31 Mar 2025.

31 Mar 2025

declared completion

18months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100001273
Registered on27 Jul 2017
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JM BLISS record 31 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Filing progress reports — 31 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Pritam Jawahar Mutha is the promoter of record on 6 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JM BLISS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
JM BLISS A BUILDING1G+531 Mar 2020
JM BLISS BUILDING B1G+101 Jan 2021
JM BLISS CLUB HOUSE1G+1-
JM BLISS C BUILDING1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2021CHAKAN NAGARPARISHAD HAS FAILED TO GIVE TIMELY APPROVALS. INITIALLY THEY CITED REASONS THAT THEIR DP PLAN REVISION IS UNDER CONSIDERATION. DUE TO THIS WE ARE NOT ABLE TO GET FULL P
30 Mar 202131 Mar 2025CHAKAN NAGARPARISHAD HAS FAILED TO GIVE TIMELY APPROVALS. INITIALLY THEY CITED REASONS THAT THEIR DP PLAN REVISION IS UNDER CONSIDERATION. DUE TO THIS WE ARE NOT ABLE TO GET FULL P

Location, Land & Connectivity

Located at Eiffel City, Shikrapur Chakan Talegaon, Pune City, Pune, 410501. Per the filed land record, the plot is bounded to the north by 1443, to the south by NALA, to the east by 12M ROAD and to the west by 1436. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~104 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park104 km
Baner–Balewadi belt109 km
Pune Junction / city centre120 km
Pune Int'l Airport (Lohegaon)122 km
Kharadi / EON IT Park125 km
Magarpatta / Hadapsar IT125 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chakan

Vallabh Heights
possession by Sep 2026 · G R Developers
Shree Samarth Shrushti
possession by Sep 2026 · Jagdamba Developers
Swapnapurti Heights
Not filing quarterly progress reports · possession by Oct 2026 · B R Developers
Richmond
possession by Oct 2026 · Coral Shubh Builders
Mungase Towers
possession by Dec 2026 · Mr Santosh Vasudev Mungase
Chakan High Street
possession by Dec 2026 · Chakan Business HUB LLP

Major developers building in Chakan

Other RERA-registered projects in Pune

Jogeshwari Krupa Sahakari Gruhrachna Sanstha Maryadit
declared completion Jun 2025 · Kalyani Developers
Jogeshwari Residency
possession by Mar 2028 · Jayraj Builders
Joy On The Tree Tops Project A
possession by Mar 2030 · Gera Projects Private Limited
Joytown E Building
possession by Dec 2028 · Shreemangal Vishram Developers
Joytown F Building
possession by Dec 2027 · Shreemangal Vishram Developers
Joytown Plots
declared completion Dec 2024 · Shreemangal Vishram Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026