Pune/Project record

MahaRERA · the public record

MADHUPUSHPA

PIRANGUT · GIRISH MADHUKAR RATHI PROP NG RATHI ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100007885

Delivery and registration

When is the project declared for completion?

MADHUPUSHPA is registered with MahaRERA as P52100007885 and the promoter has declared completion for 29 Dec 2020.

29 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100007885
Registered on18 Aug 2017
Promoter-declared completion29 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MADHUPUSHPA record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Girish Madhukar Rathi is the promoter of record on 88 projects registered with MahaRERA, 17 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

88projects

registered with MahaRERA

17flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MADHUPUSHPA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
A1G+730 Jun 2019
B1G+730 Jun 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2020DUE TO DELAY IN SANCTION OF ADDITIONAL FSI DURING THE PROCESS OF ROAD HANDOVER (RP ROAD) BY GOVT. IT NEARLY TOOK ONE AND HALF YEAR OF PERIOD.

Location, Land & Connectivity

Located at PIRANGUT, PAUD ROAD, Pune City, Pune, 412115. Per the filed land record, the plot is bounded to the north by PIRANGUT GAOTHAN, to the south by AMENITY SPACE AND PROPOSED RP ROAD, to the east by ENTRANCE OF PROJECT AND GAT NO 865 and to the west by GAT NO 867. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~102 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park102 km
Baner–Balewadi belt107 km
Pune Junction / city centre118 km
Pune Int'l Airport (Lohegaon)119 km
Kharadi / EON IT Park123 km
Magarpatta / Hadapsar IT123 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhugaon

Manas Valley Phase II
possession by Oct 2026 · Balaji Kimaya Associates
Plot NO. B-01 TO B-21 Viva,pirangut,pune
possession by Nov 2026 · Pact Real Estate Private Limited
Frangipani, Viva, Pirangut
Deregistered by MahaRERA · possession by Nov 2026 · K Raheja Corp Real Estate Private Limite
Asmi Pride
possession by Dec 2026 · M/S Icon Developers
Madhuban
possession by Dec 2026 · NG Rathi Estate
Plumeria, Viva, Pirangut
Deregistered by MahaRERA · possession by Dec 2026 · K Raheja Corp Real Estate Private Limite

Major developers building in Bhugaon

Other RERA-registered projects in Pune

Madhur Aangan
declared completion Jan 2024 · Shree SAI Developers
Madhura
possession by Apr 2030 · Belvalkar Ventures LLP
Madhura Apartment
declared completion Jun 2024 · Sathe Shah Developers
Madhura Builders AND Developers Bldg -A
declared completion Jun 2021 · Shekhar Narayan More
Madhurangan Apartment
declared completion Sep 2020 · Shri Yogesh Prabhakar Dhole
Madhusagar
declared completion Jun 2026 · Siddhashila Ventures LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026