Pune/Project record

MahaRERA · the public record

Manas Valley Phase 1

Bhukum · Balaji Kimaya Associates

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100004248

Delivery and registration

When is the project declared for completion?

Manas Valley Phase 1 is registered with MahaRERA as P52100004248 and the promoter has declared completion for 31 Dec 2020.

31 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100004248
Registered on09 Aug 2017
Promoter-declared completion31 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Manas Valley Phase 1 record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Manas Valley Phase 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
Building A1G+831 Dec 2018
Building B1G+931 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020We have started the process for application for completion certificate for the project, however we would not be able to obtain completion certificate till the given completion date
30 Apr 202030 Apr 2020all the construction work has been completed but the completion certificate has not been received.as Some NOC's are Pending.we make a humble statement the responsible committee of
30 Apr 202031 Dec 2020Our project is in pink zone for that we required noc from the Ministry of Defense. we are done all necessary process to obtain noc from Ministry of Defense. Due to covid19 outbreak

Location, Land & Connectivity

Located at Bhukum, Bhukum, Haveli, Pune, 412115. Per the filed land record, the plot is bounded to the north by Gat No55and42 Punepaud Road State Highway 60MtWide, to the south by GAT No 53 Part, to the east by GAT No 58and52 and to the west by GAT No 56and57Part. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt9 km
Hinjewadi Rajiv Gandhi IT Park10 km
Pune Junction / city centre16 km
Magarpatta / Hadapsar IT22 km
Pune Int'l Airport (Lohegaon)23 km
Kharadi / EON IT Park24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhugaon

Manas Valley Phase II
possession by Oct 2026 · Balaji Kimaya Associates
Plot NO. B-01 TO B-21 Viva,pirangut,pune
possession by Nov 2026 · Pact Real Estate Private Limited
Frangipani, Viva, Pirangut
Deregistered by MahaRERA · possession by Nov 2026 · K Raheja Corp Real Estate Private Limite
Asmi Pride
possession by Dec 2026 · M/S Icon Developers
Madhuban
possession by Dec 2026 · NG Rathi Estate
Plumeria, Viva, Pirangut
Deregistered by MahaRERA · possession by Dec 2026 · K Raheja Corp Real Estate Private Limite

Major developers building in Bhugaon

Other RERA-registered projects in Pune

Manas Valley Phase II
possession by Oct 2026 · Balaji Kimaya Associates
Manasi
declared completion Dec 2025 · Abhilasha Developers
Mandai Complex
declared completion Apr 2024 · NEW Manikraj Developers
Mandke Advantage Homes
declared completion Aug 2024 · M/s Sudhir Mandke Developers
Mandke Business Centre
declared completion Dec 2021 · Vyankatesh Vasudeo Mandke
Manek Regency
declared completion Jun 2026 · B. U. Bhandari Landmarks

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026