OMKAR HIGHTS

Pune · OMKAR DEVELOPERS AND BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

15 Aug 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

15 Aug 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100009802

Delivery and registration

When is the project declared for completion?

OMKAR HIGHTS is registered with MahaRERA as P52100009802 and the promoter has declared completion for 15 Aug 2019.

15 Aug 2019

declared completion

85months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100009802
Registered on22 Aug 2017
Promoter-declared completion15 Aug 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OMKAR HIGHTS record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Omkar Developers is the promoter of record on 162 projects registered with MahaRERA, 23 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

162projects

registered with MahaRERA

23flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for OMKAR HIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
A1G+7-
B1G+5-
C1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Pmc Court4922007Hearing Is Going On
Dist Court Pune612010Hearing Is Going On
Pmc Court5782004Hearing Is Going On

Location, Land & Connectivity

Located at Pune City, Pune, 411001. Per the filed land record, the plot is bounded to the north by RIVER AND PILLE PLOT, to the south by ROAD AND NOOR MAHAMAD, to the east by RAVIRAJ SOCIETY and to the west by TILEKARBHALERAO PLOT. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre2 km
Magarpatta / Hadapsar IT5 km
Pune Int'l Airport (Lohegaon)6 km
Kharadi / EON IT Park6 km
Baner–Balewadi belt12 km
Hinjewadi Rajiv Gandhi IT Park17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Omkar Developers AND Builders project & its RERA track record →

Other RERA-registered projects in Ghorpadi

Royal Glen
possession by Sep 2026 · Stargaze Buildcon
Ganga Bhagyoday E Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Ganga Bhagyoday F Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Boulevard Tower A2
possession by Dec 2026 · Bramhacorp Limited
Casaverde
possession by Dec 2026 · Skyboat Infrastructure Unit 1 LLP
Eternia Phase 2
possession by Dec 2026 · Venturespro Projects LLP

Major developers building in Ghorpadi

Other RERA-registered projects in Pune

Omkar Meadows
declared completion Jun 2018 · Omkar Lifespaces
Omkar Meghdoot Residency
possession by Mar 2027 · Omkar Landmarks
Omkar Nandan
declared completion Jan 2021 · Phoenix Enterprises
Omkar Nirvana
declared completion Dec 2021 · Omkar Lifespaces
Omkar Residency
possession by Sep 2026 · Prerna Group
Omkar Skyline
possession by Dec 2028 · Skyline Buildcon

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.