Orchards and Gardens Phase-I by Saga Ventures

P52100027774 · Kanhe · promoter Saga Ventures

Certificate SignedDue 21 Jun 2024

Delivery & Registration

MahaRERA registrationP52100027774
Registered on03 Jan 2021
Promoter-declared completion21 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Saga Ventures is the promoter of record on 159 projects, of which 13 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
A-31G+521 Dec 2023
C11G+521 Dec 2023
Row House No 11G+121 Dec 2023
Row House No 21G+121 Dec 2023
Row House No 31G+121 Dec 2023
Row House No 41G+121 Dec 2023
Row House No 51G+121 Dec 2023
Row House No 61G+121 Dec 2023
Row House No 71G+121 Dec 2023
Row House No 81G+121 Dec 2023
Row House No 91G+121 Dec 2023
Row House No 101G+121 Dec 2023
Row House No 111G+121 Dec 2023
Row House No 121G+121 Dec 2023
Twin House No 11G+121 Dec 2023
Twin House No 21G+121 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Kanhe, Kanhe, Mawal, Pune, 412106. Per the filed land record, the plot is bounded to the north by Railway Line, to the south by Gat No 48 and Gat No 49 and Road, to the east by Gat No 52 and to the west by Gat No 25 and Gat No 43. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vadgaon Maval

Presidential Park Phase 2
possession by Oct 2026 · Oneness Realtors
Samarth Heights
possession by Dec 2026 · Swamisamarth Developers
Osian Lifelands Grande
possession by Dec 2026 · M/s Prime Realty
Residential Building On CTS No 107/1p -Girivar Residency
possession by Dec 2026 · Shrivar Builders LLP
Sahyadri Complex
possession by Dec 2026 · Luxuriant Group
Surya Heights
possession by Dec 2026 · SSB Developer

Major developers building in Vadgaon Maval

Other RERA-registered projects in Pune

Orchid
declared completion Aug 2023 · Belmont Realty
Orchid A Wing
possession by Dec 2027 · Vedanti DIA Associates
Orchid City Building A
declared completion Jun 2019 · S S Associates
Orchid Homes
possession by Dec 2026 · Aradhya Developers
Orchid Nest B Building
declared completion Dec 2022 · Orchid Ventures
Orchid Plaza
declared completion Jun 2025 · M K Buildcon

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026