Pune/Project record

MahaRERA · the public record

Orchards and Gardens Phase-I by Saga Ventures

Kanhe · Saga Ventures

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

21 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

21 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100027774

Delivery and registration

When is the project declared for completion?

Orchards and Gardens Phase-I by Saga Ventures is registered with MahaRERA as P52100027774 and the promoter has declared completion for 21 Jun 2024.

21 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100027774
Registered on03 Jan 2021
Promoter-declared completion21 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Orchards and Gardens Phase-I by Saga Ventures record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Saga Ventures is the promoter of record on 176 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

176projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Orchards and Gardens Phase-I by Saga Ventures in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
A-31G+521 Dec 2023
C11G+521 Dec 2023
Row House No 11G+121 Dec 2023
Row House No 21G+121 Dec 2023
Row House No 31G+121 Dec 2023
Row House No 41G+121 Dec 2023
Row House No 51G+121 Dec 2023
Row House No 61G+121 Dec 2023
Row House No 71G+121 Dec 2023
Row House No 81G+121 Dec 2023
Row House No 91G+121 Dec 2023
Row House No 101G+121 Dec 2023
Row House No 111G+121 Dec 2023
Row House No 121G+121 Dec 2023
Twin House No 11G+121 Dec 2023
Twin House No 21G+121 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Kanhe, Kanhe, Mawal, Pune, 412106. Per the filed land record, the plot is bounded to the north by Railway Line, to the south by Gat No 48 and Gat No 49 and Road, to the east by Gat No 52 and to the west by Gat No 25 and Gat No 43. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vadgaon Maval

Presidential Park Phase 2
possession by Oct 2026 · Oneness Realtors
Samarth Heights
possession by Dec 2026 · Swamisamarth Developers
Osian Lifelands Grande
possession by Dec 2026 · M/s Prime Realty
Residential Building On CTS No 107/1p -Girivar Residency
possession by Dec 2026 · Shrivar Builders LLP
Sahyadri Complex
possession by Dec 2026 · Luxuriant Group
Surya Heights
possession by Dec 2026 · SSB Developer

Major developers building in Vadgaon Maval

Other RERA-registered projects in Pune

Orchid A Wing
possession by Dec 2027 · Vedanti DIA Associates
Orchid Homes
possession by Dec 2026 · Aradhya Developers
Orchid Nest B Building
declared completion Dec 2022 · Orchid Ventures
Orchids
declared completion Jun 2026 · SAI Balaji Constructions
Oriana
declared completion Mar 2018 · M/s.kishor Builders Promoters And Develo
Oriana
possession by Dec 2028 · Fortune Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026