Pune/Project record

MahaRERA · the public record

OXYGEN VALLY ANEX

Pune · SHRUSHTI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Apr 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Apr 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100005723

Delivery and registration

When is the project declared for completion?

OXYGEN VALLY ANEX is registered with MahaRERA as P52100005723 and the promoter has declared completion for 30 Apr 2019.

30 Apr 2019

declared completion

89months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100005723
Registered on11 Aug 2017
Promoter-declared completion30 Apr 2019
Current statusCertificate Signed
Against todayabout 89 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OXYGEN VALLY ANEX record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shrushti Developers is the promoter of record on 41 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

41projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for OXYGEN VALLY ANEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
Oxygen Vally Anex1G+3-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2019The Construction of the building is completed as per the sanctioned plan, however the survey of the building to be conducted by the Mamledar Office is taking time and due to this t

Location, Land & Connectivity

Located at Haveli, Pune, 412307. Per the filed land record, the plot is bounded to the north by H NO 29, to the south by 6 mt internal road, to the east by H NO 29 and to the west by H NO 35. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT4 km
Kharadi / EON IT Park6 km
Pune Junction / city centre10 km
Pune Int'l Airport (Lohegaon)10 km
Baner–Balewadi belt21 km
Hinjewadi Rajiv Gandhi IT Park26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shrushti Developers is the promoter on 15 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shrushti Developers project & its RERA track record →

Other flagged projects by Shrushti Developers

Other RERA-registered projects in Shewalewadi

GRM Avighna Apartment
possession by Sep 2026 · GRM Buildcon
Anand Park
possession by Dec 2026 · Shweta Vikas Bire
Godrej Sky Greens Phase 1
possession by Dec 2026 · Manjari Housing Projects LLP
Godrej Sky Greens Phase 2
possession by Dec 2026 · Manjari Housing Projects LLP
Joyville Hadapsar Annexe Phase 16
possession by Dec 2026 · Joyville Shapoorji Housing Private Limit
Joyville Hadapsar Annexe Phase 18
possession by Dec 2026 · Joyville Shapoorji Housing Private Limit

Major developers building in Shewalewadi

Other RERA-registered projects in Pune

Oxygreen Residency
declared completion Mar 2019 · OM SAI Shriniwas Infrastructure Private
Oxygreens
possession by Dec 2028 · S J Buildcon
Oxyzen
possession by Mar 2029 · S Square Landmark
Oyster
possession by Dec 2030 · Oyster Land Developers LLP
Ozarde Complex
declared completion Dec 2018 · Onkar Developers
Ozone 24
declared completion Dec 2021 · Milind Bhagwat Pokharkar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.