MahaRERA Property Intelligence · Pune

VTP DOLCE VITA Phase 1

P52100051819 · Manjari Kh · promoter Ashdan Developers Private

Certificate SignedDue 31 Dec 2028

Delivery & Registration

MahaRERA registrationP52100051819
Registered on07 Jul 2023
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today29 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ashdan Developers Private is the promoter of record on 17 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~53.6% of the estimated project cost incurred as of the last certificate (₹174.04 Cr spent against a ₹324.46 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 727 homes filed with MahaRERA, 668 are sold/booked (664 with registered agreements + 4 booked) and 59 remain available (~92% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹583.58 Cr in agreement value so far. Of that, ₹377.34 Cr (~65%) is already collected, ₹203.91 Cr receivable — a read on how far along these sales really are. Note: the project registers 736 homes in total, but this sold/unsold inventory filing covers only 727 of them — the other 9 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 668 registered agreements, the effective carpet rate is ₹10,616/sqft (typical range ₹9,976–₹12,107) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

⚠ The inventory filing also declares: 9 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+35 and 736 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Tower 11G+3419231 Dec 2028
Tower 21G+3420331 Dec 2028
Tower 31G+3413731 Dec 2028
Tower 41G+3520431 Dec 2028

Unit mix on the filing: 704 residential and 32 non-residential (shops/offices).

Complaints & Orders

12 complaints are on the MahaRERA record for this project, with orders passed in 8. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000026961418/10/2023Kumar Abhishek vs VTP Realty Ashdhan Developers Pvt ltdpending / no order on file
CC1240073211/11/2024Ashdan Developers Private Limited vs NASIR NANHUMIYA SAYYADorder passed
CC1240073311/11/2024Ashdan Developers Private Limited vs SHILPA ARVIND TUPE (ALLOTTEE)order passed
CC1240073411/11/2024Ashdan Developers Private Limited vs SUJATA ROHIT JAGTAP (ALLOTTEE)order passed
CC1250095819/03/2025Ashdan Developers Private Limited vs Prashant Patil (Allottee)order passed
CC1250095919/03/2025Ashdan Developers Private Limited vs Prashant Patil (Allottee)order passed
CC1250096019/03/2025Ashdan Developers Private Limited vs Arun Mohanrao Rasal (Allottee)order passed
CC1260058002/02/2026Ashdan Developers Private Limited vs Mrs Shilpa Arvind Tupeorder passed
CC1260058302/02/2026Ashdan Developers Private Limited vs Mrs Sujata Rohit Jagtaporder passed
CC1260121506/03/2026Ashdan Developers Private Limited vs MR PRASHANT PATIL (ALLOTTEE)pending / no order on file
CC1260121606/03/2026Ashdan Developers Private Limited vs MR PRASHANT PATIL(ALLOTTEE)pending / no order on file
CC1260121806/03/2026Ashdan Developers Private Limited vs MD SULTAN AHMAD (allottee)pending / no order on file

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Senior Division Pune4942008Pending
Bombay High Court4792008Ongoing
Joint C.J.S.D And Addl C.J.M Pune4942008Ongoing

Location, Land & Connectivity

Located at Manjari Kh, Awhal Wadi Road, Haveli, Pune, 412307. Per the filed land record, the plot is bounded to the north by S No 137, to the south by S No 133, to the east by S No 123 and 132 and to the west by 24M Wide Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Kharadi / EON IT Park5 km
Magarpatta / Hadapsar IT6 km
Pune Int'l Airport (Lohegaon)8 km
Pune Junction / city centre11 km
Baner–Balewadi belt22 km
Hinjewadi Rajiv Gandhi IT Park26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ashdan Developers Private Limited is the promoter on 10 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Ashdan Developers Private Limited project & its RERA track record →

Other flagged projects by Ashdan Developers Private Limited

Ashdan Developers Private Limited
FlaggedPune
Ashdan Developers Private Limited
FlaggedPune
Ashdan Developers Private Limited
FlaggedPune
Ashdan Developers Private Limited
FlaggedPune
Ashdan Developers Private Limited
FlaggedPune
Ashdan Developers Private Limited
FlaggedPune

Other RERA-registered projects in Shewalewadi

Mango Tree Villa Phase 1
possession by Jul 2026 · Palchin Real Estates Private Limited
GRM Avighna Apartment
possession by Sep 2026 · GRM Buildcon
Anand Park
possession by Dec 2026 · Shweta Vikas Bire
Godrej Sky Greens Phase 1
possession by Dec 2026 · Manjari Housing Projects LLP
Godrej Sky Greens Phase 2
possession by Dec 2026 · Manjari Housing Projects LLP
Joyville Hadapsar Annexe Phase 16
possession by Dec 2026 · Joyville Shapoorji Housing Private Limit

Major developers building in Shewalewadi

Other RERA-registered projects in Pune

VTP Dolce Vita Phase 2
possession by Jun 2029 · Ashdan Developers Private Limited
VTP Dolce Vita Phase 3
possession by Jun 2029 · Ashdan Developers Private Limited
VTP Dolce Vita Phase 4
possession by Jun 2029 · Ashdan Developers Private Limited
VTP Euphoria Phase 1
possession by Dec 2026 · Ashdan Developers Private Limited
VTP Euphoria Phase 2
possession by Jun 2027 · Ashdan Developers Private Limited
VTP Euphoria Phase 3
possession by Mar 2028 · Ashdan Developers Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026