25 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

25 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100051772

Delivery and registration

When is the project declared for completion?

PANCHATATVA VITTHAL PARK is registered with MahaRERA as P52100051772 and the promoter has declared completion for 25 Sep 2023.

25 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100051772
Registered on27 Jun 2023
Promoter-declared completion25 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PANCHATATVA VITTHAL PARK record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In PANCHATATVA VITTHAL PARK, 8 of 17 plots filed with MahaRERA are recorded as sold or booked, about 47%, and 9 remain available.

47%sold

8 of 17 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PANCHATATVA VITTHAL PARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at zendewadi, Near Vitthal Stachu , Haveli, Pune, 412201. Per the filed land record, the plot is bounded to the north by Part of Gat No392 property, to the south by Part of Gat No 392 Property, to the east by Road and to the west by Properties Gat No 391 392 393. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Magarpatta / Hadapsar IT15 km
Kharadi / EON IT Park17 km
Pune Junction / city centre20 km
Pune Int'l Airport (Lohegaon)21 km
Baner–Balewadi belt30 km
Hinjewadi Rajiv Gandhi IT Park35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Loni Kalbhor

Arvan Residency
possession by Dec 2026 · Sanskruti Developers
Keshavyog Residency
possession by Dec 2026 · Siddhivinayak Builders
Muktai Park Phase II
possession by Dec 2026 · Shivshakti Buildcon
Platinum Nirvana
possession by Dec 2026 · Platinum Developers
Swami Homes
possession by Jan 2027 · S S Developers
Krishnai Residency
possession by Mar 2027 · Ivana Properties

Other RERA-registered projects in Pune

Panchawati
declared completion Jan 2021 · D AND P Associates
Panchratna
possession by Jun 2027 · Chaphalkar Karandikar Developers
Panchratna Hills
declared completion Apr 2023 · Panchratna Associates
Panchratna Hills Phase 2
declared completion Jun 2026 · Panchratna Construction
Panchsheel Garden Building - A
declared completion Jun 2025 · Shankar Dattatray Kemse
Panchsheel Garden Building B
possession by May 2027 · Shankar Dattatray Kemse

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.