MahaRERA Property Intelligence · Pune

Prem Eleete

P52100051676 · Pimpri Chinchwad · promoter Pooja Enterprises Through

Certificate SignedDue 30 Apr 2026

Delivery & Registration

MahaRERA registrationP52100051676
Registered on27 Jun 2023
Promoter-declared completion30 Apr 2026
Current statusCertificate Signed
Against todayabout 3 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Pooja Enterprises Through is the promoter of record on 3 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~100.0% of the estimated project cost incurred as of the last certificate (₹3.32 Cr spent against a ₹3.32 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 13 homes filed with MahaRERA, 0 are sold/booked and 13 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1100530 sqft (49.25 sqm)₹52.36 Lakh
Floor 2200530 sqft (49.25 sqm)₹52.36 Lakh
Floor 2201530 sqft (49.25 sqm)₹52.32 Lakh
Floor 3300530 sqft (49.25 sqm)₹52.36 Lakh
Floor 3301530 sqft (49.25 sqm)₹52.32 Lakh
Floor 4400530 sqft (49.25 sqm)₹52.36 Lakh
Floor 4401530 sqft (49.25 sqm)₹52.32 Lakh
Floor 5500530 sqft (49.25 sqm)₹54.98 Lakh
Floor 5501530 sqft (49.25 sqm)₹54.94 Lakh
Floor 6600530 sqft (49.25 sqm)₹54.98 Lakh
Floor 6601530 sqft (49.25 sqm)₹54.94 Lakh
Floor 7700530 sqft (49.25 sqm)₹54.98 Lakh
Floor 7701530 sqft (49.25 sqm)₹54.94 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 13 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
B Wing1G+71330 Apr 2026

Unit mix on the filing: 13 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Pimpri Chinchwad, Pimpri Chinchwad, Haveli, Pune, 411018. Per the filed land record, the plot is bounded to the north by Road, to the south by Mandir and PCMC office, to the east by Road and to the west by Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pimpri

Stella Apex
possession by Oct 2026 · Vastuspace Realty Promoters AND Develope
Dharampal Corporate Avenue
possession by Dec 2026 · Surender Dharampal Agarwal
Pristine Palazzo
possession by Dec 2026 · Kanha Developers
Skylish Vaastuu
possession by May 2027 · Skylish Bluediamond Innfrracon
Santoshi Mata Complex
possession by Aug 2027 · Njhb Properties
Mahindra Nestalgia
possession by Aug 2027 · Mahindra Bloomdale Developers Limited

Major developers building in Pimpri

Other RERA-registered projects in Pune

Prem Mannat
declared completion Dec 2021 · Geeta Builder Arihant Venture
Premanand-A
possession by Dec 2027 · Gangotree Homes
Premanand-B
possession by Dec 2027 · Gangotree Homes
Premia B-1 Phase II
declared completion Oct 2018 · C.d. Developers
Premia C-1 Phase I
declared completion Dec 2017 · C.d. Developers
Premier Tower - Solitaire World
declared completion Dec 2021 · Classic Promoters And Builders Private L

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026