Pune/Project record

MahaRERA · the public record

Rajmata Sindhunagari Phase I

Pune · Rajmata Constructios

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014060

Delivery and registration

When is the project declared for completion?

Rajmata Sindhunagari Phase I is registered with MahaRERA as P52100014060 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014060
Registered on07 Nov 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Rajmata Sindhunagari Phase I record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Rajmata Constructios is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Rajmata Sindhunagari Phase I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
A21G+6-
B11G+6-
B21G+6-
B31G+6-
H1G+6-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Rajmata Sindhunagari Phase I, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001073229/12/2017Ganpati. B. Desai vs Krishna Ramesh Hakkeorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2021We are facing labour problems since October 2019.Meanwhile Covid-19 crop-up . We were unable to file our extension in January 2020 due to the illness of active partner of th

Location, Land & Connectivity

Located at Pune City, Pune, 411018. Per the filed land record, the plot is bounded to the north by Remaining Area of 178, to the south by Remaining Area of 178, to the east by Adjacent Nala and to the west by Internal Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT7 km
Kharadi / EON IT Park10 km
Pune Junction / city centre13 km
Pune Int'l Airport (Lohegaon)14 km
Baner–Balewadi belt23 km
Hinjewadi Rajiv Gandhi IT Park29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pimpri

Stella Apex
possession by Oct 2026 · Vastuspace Realty Promoters AND Develope
Dharampal Corporate Avenue
possession by Dec 2026 · Surender Dharampal Agarwal
Skylish Vaastuu
possession by May 2027 · Skylish Bluediamond Innfrracon
Santoshi Mata Complex
possession by Aug 2027 · Njhb Properties
Bramha Sky Uzuri Phase 2
possession by Dec 2027 · Bramha Leisures PVT LTD
Kohinoor World Tower Phase II
possession by Dec 2027 · Godiva Properties Private Limited

Major developers building in Pimpri

Other RERA-registered projects in Pune

Rajmudra Heights
declared completion Dec 2024 · Sudhir Sadashiv Dighe
Rajmudra Nagari
possession by Dec 2030 · Heritage Brothers Construction
Rajmudra Phase 1 And 2
declared completion Nov 2023 · Rajmudra Developers
Rajnakshatra Palace
possession by Mar 2027 · Devgiri Buildcon
Rajnandini Complex
declared completion Dec 2021 · Rajnandini Construction
Rajnandini Heights
declared completion Dec 2021 · Rajnandini Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026