Pune/Project record

MahaRERA · the public record

RAJYOG

NEAR MAASA HOTEL MUNDHWA · VISHAL MARUTI NALAWADE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

10units filed as unsoldInventory · 17 September 2026
31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
10registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100020439

Delivery and registration

When is the project declared for completion?

RAJYOG is registered with MahaRERA as P52100020439 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100020439
Registered on10 Apr 2019
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAJYOG record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vishal Maruti Nalawade is the promoter of record on 12 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In RAJYOG, ₹2.35 Cr of a declared ₹2.35 Cr estimated project cost is reported as incurred, about 100.0%, as at the last certified filing with MahaRERA.

100.0%

₹2.35 Cr

of ₹2.35 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In RAJYOG, 0 of 10 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 10 remain available.

0%sold

0 of 10 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 11849 sqft (78.87 sqm)₹69.85 Lakh
Floor 12852 sqft (79.15 sqm)₹70.10 Lakh
Floor 23849 sqft (78.87 sqm)₹69.85 Lakh
Floor 24852 sqft (79.15 sqm)₹70.10 Lakh
Floor 35849 sqft (78.87 sqm)₹69.85 Lakh
Floor 36852 sqft (79.15 sqm)₹70.10 Lakh
Floor 47849 sqft (78.87 sqm)₹69.85 Lakh
Floor 48852 sqft (79.15 sqm)₹70.10 Lakh
Floor 510852 sqft (79.15 sqm)₹70.10 Lakh
Floor 59849 sqft (78.87 sqm)₹69.85 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAJYOG in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 17 September 2026

What the filings record, home by home

Read from MahaRERA on 17 September 2026

No home in RAJYOG carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 10 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 8,228 a sq ft typical, over Rs 8,228 to Rs 8,228.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 10 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 10 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 10 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
RAJYOG1G+610-

Unit mix on the filing: 10 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2024Lack of manpower and labour supply post covid time. Most of the North Indian labourers were away and hence we had a very bad time to re establish the work momentum.
31 Dec 202431 Dec 2025Delay due to Some Technical Glitches and Pending Permissions

Location, Land & Connectivity

Located at NEAR MAASA HOTEL MUNDHWA, MUNDHWA ROAD, Pune City, Pune, 411036. Per the filed land record, the plot is bounded to the north by PLOT NO 8, to the south by PLOT NO 10, to the east by 9 M WIDE ROAD and to the west by SR NO 91. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Magarpatta / Hadapsar IT2 km
Kharadi / EON IT Park3 km
Pune Junction / city centre5 km
Pune Int'l Airport (Lohegaon)6 km
Baner–Balewadi belt16 km
Hinjewadi Rajiv Gandhi IT Park21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mundhwa

Casa Elanza
possession by Sep 2026 · Parmaz Green Realty LLP
Platinum Capital Office - Phase I
possession by Sep 2026 · A Advani Properties LLP
The Golden Bell
Not filing quarterly progress reports · possession by Dec 2026 · Panchshil Hotels Pvt Ltd
ACE Villas
possession by Dec 2026 · Jhamtani Realty Private Limited
Anandtara Iris Residences Phase I
possession by Dec 2026 · Anandtara Infrastructure
Anandtara Iris Residences Phase II
possession by Dec 2026 · Anandtara Infrastructure

Major developers building in Mundhwa

Other RERA-registered projects in Pune

Rajyog
possession by Jun 2027 · Shree Vyankatesh Landmarks
Rajyog C Wing
possession by Dec 2026 · Santosh Shankar Tathe
Rajyog Residency
declared completion Mar 2023 · Rajyog Properties
Rajyog Residency
declared completion Dec 2019 · Balaji Vikram Aware
Rajyog Royal
declared completion Jun 2021 · Rajyog Builders And Developers
Rajyog Vitthal
declared completion Jan 2026 · Vitthal Properties

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026