MahaRERA · the public record
SAI GARDEN
Pune · Chandrakant Sarjerao Shinde
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Oct 2025
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100006512
Delivery and registration
When is the project declared for completion?
SAI GARDEN is registered with MahaRERA as P52100006512 and the promoter has declared completion for 31 Oct 2025.
31 Oct 2025
declared completion
11months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100006512 |
| Registered on | 14 Aug 2017 |
| Promoter-declared completion | 31 Oct 2025 |
| Current status | Certificate Signed |
| Against today | about 11 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI GARDEN record 34 quarterly progress reports since registration.
34quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Promoter record
What else is this promoter on record for?
Chandrakant Sarjerao Shinde is the promoter of record on 121 projects registered with MahaRERA, 23 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
121projects
registered with MahaRERA
23flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for SAI GARDEN in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| A Wing | 1 | G+1 | 30 Apr 2024 |
| B WIng | 1 | G+1 | 30 Apr 2024 |
| C WIng | 1 | G+1 | 30 Apr 2024 |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Jan 2020 | Non availability of necessary material and contractors within estimated time and other unavoidable circumstances. |
| 31 Jan 2020 | 30 Oct 2023 | DUE TO SHORTAGE OF FUNDS AND LESS SALE AT PROJECT. THE SALES & FUNDS COLLECTION WILL TAKE TIME.I HAVE ALREADY TAKEN EXT. ONCE & THE COMPLETION DATE OF PROJECT WAS 31-01-2020 BUT WE |
| 30 Oct 2023 | 31 Oct 2025 | Due to pandamic covid-19 there was shortage of labour during and after covid all the banking and transuction got slower which result shortage of finanace we were in financially cri |
Location, Land & Connectivity
Located at Haveli, Pune, 412106. Per the filed land record, the plot is bounded to the north by BY GAT NO 589, to the south by BY GAT NO 587, to the east by BY ROAD TOWARDS VILLAGE JAMBHUL and to the west by BY GAT NO 585. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~24 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 24 km |
| Baner–Balewadi belt | 29 km |
| Pune Junction / city centre | 39 km |
| Pune Int'l Airport (Lohegaon) | 39 km |
| Kharadi / EON IT Park | 43 km |
| Magarpatta / Hadapsar IT | 44 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.