Pune/Project record

MahaRERA · the public record

Sara Kasturi Building B

Chakan · JAGRUTSARA STRUCTURES LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100032693

Delivery and registration

When is the project declared for completion?

Sara Kasturi Building B is registered with MahaRERA as P52100032693 and the promoter has declared completion for 31 Mar 2027.

31 Mar 2027

declared completion

6months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100032693
Registered on24 Jan 2022
Promoter-declared completion31 Mar 2027
Current statusCertificate Signed
Against today6 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sara Kasturi Building B record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Jagrutsara Structures Llp is the promoter of record on 26 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

26projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sara Kasturi Building B in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
Sara Kasturi Building B1G+15-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Chakan, Chakan Talegaon road, Aurangabad, Aurangabad, 410501. Per the filed land record, the plot is bounded to the north by Next phase of Sara Kasturi, to the south by 6m wide fire drive way and Amenity space, to the east by 6m wide path way and next phase of Sara kasturi and to the west by 6m wide fire drive way. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Jagrutsara Structures LLP is the promoter on 14 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Jagrutsara Structures LLP project & its RERA track record →

Other flagged projects by Jagrutsara Structures LLP

Jagrutsara Structures LLP
FlaggedPune
Jagrutsara Structures LLP
FlaggedPune
Jagrutsara Structures LLP
FlaggedPune
Jagrutsara Structures LLP
FlaggedPune
Jagrutsara Structures LLP
FlaggedPune
Jagrutsara Structures LLP
FlaggedPune

Other RERA-registered projects in Chakan

Vallabh Heights
possession by Sep 2026 · G R Developers
Shree Samarth Shrushti
possession by Sep 2026 · Jagdamba Developers
Swapnapurti Heights
Not filing quarterly progress reports · possession by Oct 2026 · B R Developers
Richmond
possession by Oct 2026 · Coral Shubh Builders
Mungase Towers
possession by Dec 2026 · Mr Santosh Vasudev Mungase
Chakan High Street
possession by Dec 2026 · Chakan Business HUB LLP

Major developers building in Chakan

Other RERA-registered projects in Pune

Sara Kasturi Building C
possession by Dec 2032 · Jagrutsara Structures LLP
Sara Metroville A Phase II
declared completion Jun 2022 · Sara Infrastructures
Sara Metroville C Phase III
declared completion Dec 2021 · Sara Infrastructures
Sara Nilaay
possession by Dec 2030 · Jagrutsara Structures LLP
Sara Nilaay C & D
possession by Mar 2031 · Jagrutsara Structures LLP
Sara Oasis
possession by Dec 2030 · Jagrutsara Structures LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026