MahaRERA Property Intelligence · Pune

SHANTAI GREEN

P52100007325 · RAVET · promoter Vinod Tukaram Adaskar

Certificate SignedDue 31 Mar 2024

Delivery & Registration

MahaRERA registrationP52100007325
Registered on17 Aug 2017
Promoter-declared completion31 Mar 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vinod Tukaram Adaskar is the promoter of record on 58 projects, of which 7 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
SHANTAI GREEN1G+1131 Mar 2022

Complaints & Orders

4 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000005383325/12/2019Dheeraj Sharad Kshatriya vs V.T.Adaskar & company through its prop Mr.VInod tukaram Adaskarorder passed
CC00500000005406925/02/2020Mrs Urmila Sandeep Patil and Mr Sandeep Pandit Patil vs M/s V.T Adaskar and Co. through its proprietor Mr Vinod Tukaram Adaskarorder passed
CC1250288216/08/2025Surekha Raju Bandpatte vs VINOD TUKARAM ADASKARorder passed
CC1260443416/07/2026Trupti Dhiraj Kshatriya vs VINOD TUKARAM ADASKARpending / no order on file

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Junior Division1447/20132013Exibit Five Pending
Sub Divisional Officer Haveli936/20132013Pending For Hearing

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Mar 202431 Mar 2024We have unable to complete project work due to COVID 19 pandemic and inventory are not sold within time.
31 Mar 202431 Dec 2021We have unable to complete project work due to COVID 19 pandemic and inventory are not sold within time.

Location, Land & Connectivity

Located at RAVET, MASKE WASTI, Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by ARUN BLUE SCHEME, to the south by CHORDIYA BUILDER, to the east by PART OF S NO 97 and to the west by 24 MTR DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park8 km
Baner–Balewadi belt12 km
Pune Junction / city centre20 km
Pune Int'l Airport (Lohegaon)20 km
Kharadi / EON IT Park24 km
Magarpatta / Hadapsar IT25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vinod Tukaram Adaskar is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Vinod Tukaram Adaskar

Vinod Tukaram Adaskar
FlaggedPune
Vinod Tukaram Adaskar
FlaggedPune

Other RERA-registered projects in Ravet

Shivratna
possession by Jul 2026 · Mr Rajan Vishram Palekar
Glorious Tathastu
possession by Jul 2026 · Glorious Buildcon
Aqua Life
possession by Aug 2026 · Legacy Lifespaces LLP
City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited

Major developers building in Ravet

Other RERA-registered projects in Pune

Shantai Green
possession by Dec 2027 · Vinod Tukaram Adaskar
Shantai Heights
declared completion Mar 2018 · Vinod Tukaram Adaskar
Shantai Heritage
declared completion Mar 2018 · Vinod Tukaram Adaskar
Shantai Park
declared completion Dec 2022 · Samarttha Landmark
Shantai Residency
declared completion Dec 2018 · JSJ Builders AND Developers
Shantai Residency
declared completion Dec 2025 · M.d.m Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026