Pune/Project record

MahaRERA · the public record

SHANTAI GREEN

RAVET · VINOD TUKARAM ADASKAR

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100007325

Delivery and registration

When is the project declared for completion?

SHANTAI GREEN is registered with MahaRERA as P52100007325 and the promoter has declared completion for 31 Mar 2024.

31 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100007325
Registered on17 Aug 2017
Promoter-declared completion31 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHANTAI GREEN record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vinod Tukaram Adaskar is the promoter of record on 69 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

69projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHANTAI GREEN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
SHANTAI GREEN1G+1131 Mar 2022

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for SHANTAI GREEN, with orders passed in 3 of them.

4complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000005383325/12/2019Dheeraj Sharad Kshatriya vs V.T.Adaskar & company through its prop Mr.VInod tukaram Adaskarorder passed
CC00500000005406925/02/2020Mrs Urmila Sandeep Patil and Mr Sandeep Pandit Patil vs M/s V.T Adaskar and Co. through its proprietor Mr Vinod Tukaram Adaskarorder passed
CC1250288216/08/2025Surekha Raju Bandpatte vs VINOD TUKARAM ADASKARorder passed
CC1260443416/07/2026Trupti Dhiraj Kshatriya vs VINOD TUKARAM ADASKARpending / no order on file

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Junior Division1447/20132013Exibit Five Pending
Sub Divisional Officer Haveli936/20132013Pending For Hearing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2021We have unable to complete project work due to COVID 19 pandemic and inventory are not sold within time.
31 Dec 202131 Mar 2024We have unable to complete project work due to COVID 19 pandemic and inventory are not sold within time.

Location, Land & Connectivity

Located at RAVET, MASKE WASTI, Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by ARUN BLUE SCHEME, to the south by CHORDIYA BUILDER, to the east by PART OF S NO 97 and to the west by 24 MTR DP ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park8 km
Baner–Balewadi belt12 km
Pune Junction / city centre20 km
Pune Int'l Airport (Lohegaon)20 km
Kharadi / EON IT Park24 km
Magarpatta / Hadapsar IT25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vinod Tukaram Adaskar is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Vinod Tukaram Adaskar

Vinod Tukaram Adaskar
FlaggedPune

Other RERA-registered projects in Ravet

City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited
Madhuban
possession by Sep 2026 · Godrej Skyline Developers Limited
OM Mangalam Chaitanya
possession by Sep 2026 · Shri Associates
OM Mangalam Disha
possession by Sep 2026 · Shri Associates

Major developers building in Ravet

Other RERA-registered projects in Pune

Shantai Green
possession by Dec 2027 · Vinod Tukaram Adaskar
Shantai Heritage
declared completion Mar 2018 · Vinod Tukaram Adaskar
Shantai Park
declared completion Dec 2022 · Samarttha Landmark
Shantais Divine Vastu
possession by Dec 2026 · Mahalaxmi Developers
Shantanu Height
possession by Dec 2026 · Shashidhar Singh
Shanti Anand
declared completion Dec 2025 · Sankalp Promoters

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026