Pune/Project record

MahaRERA · the public record

SILVER EMINENCE

LEFT BHUSARI COLONY · M/S SAI ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

11units filed as unsoldInventory · 19 September 2026
31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100054509

Delivery and registration

When is the project declared for completion?

SILVER EMINENCE is registered with MahaRERA as P52100054509 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100054509
Registered on25 Jan 2024
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SILVER EMINENCE record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SILVER EMINENCE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 September 2026

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 3 homes carry one, and 11 of the 14 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
101946 sqftRs 1.1885 cr to Rs 1.3268 cr2 filed on this stack, floors 6–7

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Silver Eminence1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at LEFT BHUSARI COLONY, SR NO 95/1B, PLOT NO 56, Haveli, Pune, 411038. Per the filed land record, the plot is bounded to the north by SR NO 102, to the south by 30 FT COLONY ROAD, to the east by PLOT NO 55 and to the west by PLOT NO 57. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt6 km
Pune Junction / city centre9 km
Hinjewadi Rajiv Gandhi IT Park11 km
Magarpatta / Hadapsar IT14 km
Pune Int'l Airport (Lohegaon)16 km
Kharadi / EON IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other flagged projects by Shankar Dattatraya Kemse

Shankar Dattatraya Kemse
FlaggedPune

Other RERA-registered projects in Kothrud

Arunali
possession by Sep 2026 · Badhekar Properties
Guruvaibhav CO-Op.housing Society Limited
possession by Sep 2026 · Shreepad Associates
Prathamesh Co-Op Housing Soc
possession by Sep 2026 · Joshi Associates
State Bank OF India Snehdeep Chsl
possession by Sep 2026 · Kotibhaskar Infrastructures &develop
Vaibhavshree AND Indira Priyadarshani
possession by Sep 2026 · Pride Properties & Infrastructure
Yakshanagari CO Operative Housing Society LTD
possession by Sep 2026 · VSA Intezine LLP

Major developers building in Kothrud

Other RERA-registered projects in Pune

Silver Evergreen
possession by Dec 2028 · Shivaay Developers
Silver Galaxy Phase II
possession by Dec 2028 · Silver Bliss
Silver Gardenia
possession by Dec 2031 · Silver Promoters AND Developers
Silver Heights
declared completion Dec 2024 · Shrijee Developers
Silver Karishma
declared completion May 2022 · Sawant Jadhav Associates
Silver Lavish
declared completion Mar 2026 · OM Infra AND Prapti Icon

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026