MahaRERA Property Intelligence · Pune

UNNATI ASTRIA

P52100049726 · Mukundnagar · promoter Himmat Land Holdings

Certificate SignedDue 30 Jun 2025

Delivery & Registration

MahaRERA registrationP52100049726
Registered on22 Feb 2023
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 13 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Himmat Land Holdings is the promoter of record on 79 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Unnati Astria1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202430 Jun 2025Work on site is 90% completed with only lift installation and other finishing works pending. Hence an extension of 6 months for completing the project is requested. All the allotte

Location, Land & Connectivity

Located at Mukundnagar, Mukundnagar, Pune City, Pune, 411037. Per the filed land record, the plot is bounded to the north by By Sub plot no 157 4 and 157 10 in remaining part, to the south by By 30 corporation road previously it was colony ro, to the east by By sub plot no 157 6 from same layout and to the west by By sub plot no 157 8 from same layout. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bibwewadi

Celia Phase 2
Not filing quarterly progress reports · possession by Jul 2026 · Enerrgia Developers
Ravindu
possession by Jul 2026 · Shubh Ventures
Siddhachal - A1
possession by Jul 2026 · Viraj Properties (now Known As Viraj Pro
Indian Bank Staff CO-Operative Housing Society LTD
possession by Aug 2026 · Raichandani Constructions Private Limite
Siddhi -Siddhachal
possession by Aug 2026 · Bhairav Promoters Unit Number 1
Osian Navkar
possession by Sep 2026 · Osian Realty

Major developers building in Bibwewadi

Other RERA-registered projects in Pune

Unnati-Phase 2
declared completion Dec 2023 · Sigma Realty
Unnati Phase III
declared completion Dec 2025 · Sigma Realty
Unnati Vatika
possession by Apr 2027 · M/S Unnati Lifespace
UP-Life-Phase-1-Veronica
declared completion Jun 2025 · Avior Shelters LLP
UP-Life-Phase-2-Emerald
possession by Dec 2029 · Avior Shelters LLP
UP-Life-Phase-3-Sapphire
declared completion Dec 2025 · Avior Shelters LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026