MahaRERA Property Intelligence · Pune

URBANGRAM PIRANGUT -1 BUILDING C AND D

P52100003213 · promoter S2 Realty

Certificate SignedDue 31 Jul 2019

Delivery & Registration

MahaRERA registrationP52100003213
Registered on05 Aug 2017
Promoter-declared completion31 Jul 2019
Current statusCertificate Signed
Against todayabout 84 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
C1G+1231 Jul 2019
D1G+1231 Jul 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Haveli, Pune, 412115. Per the filed land record, the plot is bounded to the north by GAT NO 1209 AND 1198, to the south by INTERNAL ROAD, to the east by CLUB HOUSE AND OPEN SPACE and to the west by AMENITY SPACE AND GAT NO 1214. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~182 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Junction / city centre182 km
Baner–Balewadi belt182 km
Magarpatta / Hadapsar IT182 km
Hinjewadi Rajiv Gandhi IT Park184 km
Kharadi / EON IT Park186 km
Pune Int'l Airport (Lohegaon)189 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

S2 Realty is the promoter on 7 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by S2 Realty

S2 Realty
Past its declared completion datePune
S2 Realty
Past its declared completion datePune
S2 Realty
Past its declared completion datePune
S2 Realty
Past its declared completion datePune

Other RERA-registered projects in Bhugaon

Balaji Krupa
possession by Jul 2026 · Santosh Dinkar Narvekar
Manas Valley Phase II
possession by Oct 2026 · Balaji Kimaya Associates
Plot NO. B-01 TO B-21 Viva,pirangut,pune
possession by Nov 2026 · Pact Real Estate Private Limited
Frangipani, Viva, Pirangut
Deregistered by MahaRERA · possession by Nov 2026 · K Raheja Corp Real Estate Private Limite
Krushnarang Residency
possession by Dec 2026 · Vastushilp Developers
Shanaya Elegance
possession by Dec 2026 · CK Associates

Major developers building in Bhugaon

Other RERA-registered projects in Pune

Urbangram Pirangut-I Building E
declared completion Jan 2021 · S2 Realty
Urbangram Pirangut-II Building F AND H
declared completion Jul 2019 · S2 Realty
Urbangram Pirangut - II Building G
declared completion Jul 2023 · S2 Realty
Urbania Mangalam
declared completion Apr 2025 · Urbania Realty
Urbanlife Plotting
declared completion Jun 2022 · Kakade Vtp Associates
Urbano
declared completion Dec 2024 · NG Rathi Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026