Pune/Project record

MahaRERA · the public record

Urja Cornerstore Building 3

Grampanchayat · Vimal Gordhanbhai Pipalia

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100005711

Delivery and registration

When is the project declared for completion?

Urja Cornerstore Building 3 is registered with MahaRERA as P52100005711 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100005711
Registered on11 Aug 2017
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Urja Cornerstore Building 3 record 37 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Vimal Gordhanbhai Pipalia is the promoter of record on 6 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Urja Cornerstore Building 3 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Urja Cornerstore Building 31G+231 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2027Dear Sir/ Madam, We have registered our Project “Urja Cornerstore Building 3” located at Plot bearing / CTS / survey no- Gut No 2440 1, Village Chakan, Taluka Khed at Chakan (CT),

Location, Land & Connectivity

Located at Grampanchayat , Nashik Hwy, Panvel, Raigarh, 410501. Per the filed land record, the plot is bounded to the north by By Land Bearing Gut No 4207 4211 4235, to the south by By Remaining Portion of the Present S No, to the east by By Land Bearing Gut No 3813 and to the west by By Land Bearing Gut No 3815. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)21 km
Hinjewadi Rajiv Gandhi IT Park23 km
Baner–Balewadi belt25 km
Kharadi / EON IT Park25 km
Pune Junction / city centre26 km
Magarpatta / Hadapsar IT29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vimal Gordhanbhai Pipalia is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Vimal Gordhanbhai Pipalia

Vimal Gordhanbhai Pipalia
FlaggedPune
Vimal Gordhanbhai Pipalia
FlaggedPune

Other RERA-registered projects in Chakan

Vallabh Heights
possession by Sep 2026 · G R Developers
Shree Samarth Shrushti
possession by Sep 2026 · Jagdamba Developers
Swapnapurti Heights
Not filing quarterly progress reports · possession by Oct 2026 · B R Developers
Richmond
possession by Oct 2026 · Coral Shubh Builders
Mungase Towers
possession by Dec 2026 · Mr Santosh Vasudev Mungase
Chakan High Street
possession by Dec 2026 · Chakan Business HUB LLP

Major developers building in Chakan

Other RERA-registered projects in Pune

Usha CO-Operative Housing Society LTD
possession by Jun 2029 · Shreeram Schemes
Usha Heights
possession by Dec 2026 · Muralidhar Hajare
Ushakkal
possession by Dec 2027 · Ranade Bagade Construction LLP
Utkarsh Avenue 3 SAI Residency Building C
declared completion Mar 2024 · Sachin Ganpatrao Taware
Utkarsh Avenue Building C
possession by Dec 2026 · Nitin Popatrao Jagtap
Utkarsh Complex
possession by Dec 2026 · Shree Swami Samarth Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026