Bangalore/Project record

K-RERA · the public record

Concorde Econex

Bengaluru East · Concorde Housing Corporation

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ3 2025 filing
86units not bookedof 110 · Q3 2025 filing
31 Mar 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

31 Mar 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Commercial units
110

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.2registered acres

93.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/311022/005385

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2026
Land area4,752 sq m (1.2 acres)
Units registered110
Tower/wing entries1
Unit mix110 × Commercial units

In context

Density93.7 units per acre
Density in context78th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units110Total inventory registered with K-RERA.
Official carpet area8,808 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area10,643 sqmUseful scale context when comparing density and project cost.
Registered land area4,752 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.24Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)214Separate filed counts; these categories may overlap and are not added together.
Covered-parking field195Separate filed counts; these categories may overlap and are not added together.
Open-parking field19Separate filed counts; these categories may overlap and are not added together.
Garage field214Separate filed counts; these categories may overlap and are not added together.
Approved plan numberDO2-KIADB-00117/21-22/BPUse this to match the sanctioned drawing set shown by the builder.
Plan approval date07-02-2022
Project start date02-05-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Commercial units110100%8,808 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A711021426.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 110 official flat/unit rows, matching the 110 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
COMMERCIAL11044.9-105.9 sqm23.2-57.5 sqm214

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
A11044.9-105.9 sqm23.2-57.5 sqm214
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
001A0COMMERCIAL67.3 sqm43.7 sqm2
002A0COMMERCIAL67.3 sqm43.7 sqm2
003A0COMMERCIAL67.3 sqm43.7 sqm2
004A0COMMERCIAL67.3 sqm43.7 sqm2
005A0COMMERCIAL67.3 sqm43.7 sqm2
006A0COMMERCIAL67.3 sqm43.7 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

12 of 43 compliance document slots are filed as Not Applicable; the remaining 31 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Mar 2026 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

3 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved16-11-2021NOC_BWSSB.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved01-10-2022NOC_KSPCB.pdf
KPTCL- BESCOMApproved08-09-2021NOC_BESCOM.pdf
Fire and SafetyApproved04-07-2022NOC_Fire.pdf
Labour and Education DepartmentApproved19-10-2022Econex CLRA.pdf
Airport Authority of IndiaApproved09-08-2021NOC_AAI.pdf
BSNL/Telecommunication DepartmentApproved30-07-2021NOC_BSNL.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantM/s.Nagendran & Co2334421994Bengaluru Urban, Karnataka - 560027
EngineerB E PruthvirajaBCCL/BL-3.6/SE-0061/21-222008Bengaluru Urban, Karnataka - 560083
ArchitectTilak ThomasCA/99/252822001Bengaluru Urban, Karnataka - 560001
ContractorConcorde Housing Corporation Pvt Ltd-2008Bengaluru Urban, Karnataka - 560078

Builder track record

RERA filing

Concorde has 21 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Concorde Housing”) (average reported construction progress 54%). 7 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹1.10 Cr collected from buyers, ₹1.04 Cr withdrawn from the project's escrow account.

Construction progress100% → 100% (+0 pts)
Units sold/booked as registered24/110 (22%)
Buyer collections in available QPRs₹1.10 Cr
Escrow withdrawals in available QPRs₹1.04 Cr (0.95x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹34.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank Jayanagar IFSC Code : UTIB0000052 Pin Code : 560041. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub5 km
Bellandur–Marathahalli belt5 km
MG Road / city centre11 km
Outer Ring Road / Manyata12 km
Electronic City15 km
Kempegowda Int'l Airport25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Concorde Housing. View Concorde Housing's full track record →
Concorde Housing has 11 projects registered in Bangalore, 4 completed.

Other projects by this builder in Bangalore

Concorde Auriga
Filing overdue · 100% built · 85% sold
Concorde Equity Phase II
Filing overdue · 95% built
Concorde Equity
Filing overdue · 100% built
Concorde Antares
On track · 66% built · 61% sold
Concorde Eleve
On track · 13% built · 14% sold

Other RERA-registered projects in Mahadevapura

Major developers building in Mahadevapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.