9%construction reportedQ1 2026 filing
92units not bookedof 387 · Q1 2026 filing
31 Mar 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q4 2025 to Q1 2026

declared completion

31 Mar 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK
220
2 BHK
167

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

5.0registered acres

77.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/110326/008519

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2030
Land area20,183 sq m (5.0 acres)
Homes registered387
Tower/wing entries2
Unit mix220 × 3 BHK, 167 × 2 BHK

In context

Density77.6 homes per acre
Density in context53rd percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units387Total inventory registered with K-RERA.
Official carpet area33,148 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area73,900 sqmUseful scale context when comparing density and project cost.
Registered land area20,183 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.74Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)387Separate filed counts; these categories may overlap and are not added together.
Covered-parking field465Separate filed counts; these categories may overlap and are not added together.
Open-parking field75Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberCC/1458/2025-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date05-03-2026
Project start date01-04-2026

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK22057%21,979 sqm
2 BHK16743%11,168 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower 12719019086.25 m
Towers 22819719789.3 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 387 official flat/unit rows, matching the 387 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
NA19067.5-116.2 sqm30.2-52.7 sqm190
2BED 2T8365.0-67.1 sqm29.4-30.3 sqm83
3 BED 3T57105.0 sqm47.7 sqm57
3 BED 2T5088.8 sqm39.9 sqm50
3 BED 2T odd488.3 sqm39.9 sqm4
2BED 2T ODD266.5 sqm30.3 sqm2
2 BED 2T ODD183.8 sqm38.5 sqm1

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Towers 219765.0-105.0 sqm29.4-47.7 sqm197
Tower 119067.5-116.2 sqm30.2-52.7 sqm190
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
11003Tower 10NA116.2 sqm52.7 sqm1
11004Tower 10NA67.5 sqm30.2 sqm1
11006Tower 10NA67.5 sqm30.2 sqm1
11007Tower 10NA116.2 sqm52.7 sqm1
11013Tower 11NA116.2 sqm52.7 sqm1
11014Tower 11NA67.5 sqm30.2 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

15 of 34 compliance document slots are filed as Not Applicable; the remaining 19 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

5 of 6 applicable approvals are on file; still outstanding: KPTCL- BESCOM. Confirm each has been granted, not merely applied for, before booking.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved16-07-2025WATER NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved10-12-2025KSPCB -CFE 10122025.pdf
KSPCB- MOEF (Above 50 Acres)Approved02-12-2025MOEF 0212025compressed.pdf
KPTCL- BESCOMApplied31-07-2025View NOC
Fire and SafetyApproved01-01-2026FIRE NOC.pdf
Airport Authority of IndiaApproved07-01-2026AIRPORT NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantROHITH S G030404S2020Bengaluru Urban, Karnataka - 560062
EngineerVinod Kumar RMIE-15531132016Bengaluru Urban, Karnataka - 560024
ArchitectAr. J. MamthaCA/2005/370872005Bengaluru Urban, Karnataka - 560024
ContractorLarsen & Toubro Limited-1913Bengaluru Urban, Karnataka - 560001

Builder track record

RERA filing

Prestige has 81 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Prestige Projects”) (average reported construction progress 66%). 53 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹24.40 Cr collected from buyers, ₹28.49 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹28.49 Cr) exceeded buyer collections (₹24.40 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress4% → 9% (+5 pts)
Units sold/booked as registered295/387 (76%)
Buyer collections in available QPRs₹39.63 Cr
Escrow withdrawals in available QPRs₹39.49 Cr (1.00x collections)
  • Construction progress moved from 4% to 9% across the filed QPR window.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹56.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank MG Road Bangalore IFSC Code : ICIC0000002 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Whitefield IT hub10 km
Bellandur–Marathahalli belt11 km
Electronic City12 km
MG Road / city centre21 km
Outer Ring Road / Manyata24 km
Kempegowda Int'l Airport36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Prestige Projects. View Prestige Projects's full track record →
Prestige Projects has 12 projects registered in Bangalore, 2 completed, 3 past RERA deadline.

Other projects by this builder in Bangalore

Aston Park @ The Prestige City
Past deadline · 83% built · 100% sold
Meridian Park Phase II @ The Prestige City
Past deadline · 93% built · 100% sold
Meridian Park Phase III @ The Prestige City
Past deadline · 93% built · 100% sold
Eden Park @ THE Prestige City
Filing overdue · 100% built · 100% sold
Meridian Park Phase I @ The Prestige City
Filing overdue · 100% built · 100% sold
Aspen Greens @ THE Prestige City
No filings

Other RERA-registered projects in Sarjapura

Major developers building in Sarjapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Fernvale @ The Prestige City?