K-RERA · the public record
Shriram Chirping Grove
Anekal · TANMATHRA AQUARELLE DEVELOPERS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Promoter-reported construction
K-RERA quarterly filings · Q3 2025 to Q3 2025
declared completion
19 Jan 2025
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
12.4registered acres
8.7registered units per acre
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1251/308/PR/200226/003310
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
In context
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered units | 108 | Total inventory registered with K-RERA. |
| Official carpet area | 18,740 sqm | Regulator-disclosed project-level carpet area, not vision-derived room sums. |
| Registered land area | 50,170 sqm | The land area attached to this K-RERA registration. |
| Sanctioned FAR/FSI | 0.87 | Higher FAR generally means a denser vertical build, subject to site layout and open-space design. |
| Registered tower/wing entries | 5 | Official tower/wing count in the K-RERA detail page. |
| Parking total (reconciled) | 108 | Separate filed counts; these categories may overlap and are not added together. |
| Open-parking field | 28 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 108 | Separate filed counts; these categories may overlap and are not added together. |
| Project start date | 20-01-2020 |
Official inventory & towers
RERA filingK-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| Row Houses | 108 | 100% | 18,740 sqm |
Registered tower / wing summary
| Tower/wing | Floors | Units | Parking | Height |
|---|---|---|---|---|
| wing A | 2 | 27 | 27 | - |
| WING B | 2 | 26 | 26 | - |
| WING C | 2 | 12 | 12 | - |
| WING D | 2 | 13 | 13 | - |
| WING E | 2 | 30 | 30 | - |
Official unit register
RERA filingK-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 108 official flat/unit rows, matching the 108 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.
By unit type
| Unit type | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| Row House | 108 | 127.7-184.9 sqm | 0.0 sqm | 108 |
By tower / wing
| Tower/wing | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| WING E | 30 | 127.7-176.8 sqm | 0.0 sqm | 30 |
| wing A | 27 | 138.3-174.3 sqm | 0.0 sqm | 27 |
| WING B | 26 | 146.2-184.9 sqm | 0.0 sqm | 26 |
| WING D | 13 | 140.5-176.5 sqm | 0.0 sqm | 13 |
| WING C | 12 | 140.5-176.5 sqm | 0.0 sqm | 12 |
Show sample official unit rows
| Unit | Tower | Floor | Type | Carpet | UDS | Parking |
|---|---|---|---|---|---|---|
| 1 | wing A | 0 | Row House | 174.3 sqm | 0.0 sqm | 1 |
| 2 | wing A | 0 | Row House | 174.3 sqm | 0.0 sqm | 1 |
| 3 | wing A | 0 | Row House | 174.3 sqm | 0.0 sqm | 1 |
| 4 | wing A | 0 | Row House | 172.6 sqm | 0.0 sqm | 1 |
| 5 | wing A | 0 | Row House | 172.6 sqm | 0.0 sqm | 1 |
| 6 | wing A | 0 | Row House | 172.6 sqm | 0.0 sqm | 1 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
2 of 23 compliance document slots are filed as Not Applicable; the remaining 21 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 19 Jan 2025, extended (Covid Extension) to 19 Oct 2025 — both dates have passed with no OC on file.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA complaint orders (3 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| Mayank Aggarwal vs TANMATHRA AQUARELLE DEVELOPERS PRIVATE LIMITED | 1) Direct the respondent to refund the booking amount of Rs. 1 Lac with interest 2) Direct the respondent to pay Rs. 10,000/- of filing this complaint. | AUTHORITY | 23/07/2024 |
| PRAMILA BISWAL DAITARI ROUT vs SHRIRAM PROPERTIES LTD | Refund of booking amount | AUTHORITY | 19/11/2024 |
| Pramod & Vidya vs M/S. TANMATHRA AQUARELLE DEVELOPERS PVT LTD;M/S.SHRIRAM PROPERTIES LTD & 50 OTHERS | Cancellation of booking and agreement due to incorrect information provided and request for full refund of about 92 lakhs + interest paid to home loan + compensation | AUTHORITY | 05/08/2024 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (2 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/220304/0009075 04-03-2022 | Refund of Token amount of Rs. 50,000 | SHRIRAM CHIRPING GROVE - 2 (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/220913/0010007 13-09-2022 | Refund for the booking cancelled with in 12 days | SHRIRAM CHIRPING GROVE - 2 (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Statutory approval status
RERA filingClean approvals profile: every applicable statutory NOC is on file — including pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC and environmental clearance are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.
7 further authority slots are marked not applicable by the regulator.
| Authority / NOC | Status | Date | File |
|---|---|---|---|
| Water supply and sewage board | Approved | 02-07-2018 | Water Supply NOC Panchayath 1.pdf |
| KSPCB- PCB (10 Acres to 125 Acres) | Approved | 23-08-2018 | 038 KSPCB 1.pdf |
| KPTCL- BESCOM | Approved | 21-01-2020 | 036 BESCOM 1.pdf |
Project team & certifications
RERA filingK-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Architect | Satyanarayana.B | - | 1997 | R.T.Nagar, Bangalore-560032 |
| Structural engineer | Bhaskar.Y | - | - | - |
Financials & Construction Progress
Financial disclosures
RERA filingLatest quarterly filing (2025-Q3): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.
| Construction progress | 100% → 100% (+0 pts) |
| Units sold/booked as registered | 108/108 (100%) |
- 100% of registered units are shown as sold/booked, but no completion certificate is on file yet.
- The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.
QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.
Declared construction cost ÷ registered units averages to ₹104.7 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.
RERA 70% project account is on file: HDFC HSR Layout (IFSC HDFC0003758, a/c …4744). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Construction photo filings
RERA filingK-RERA has 1 project-photo upload.
These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.
Location & Connectivity
The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Whitefield IT hub | 14 km |
| Electronic City | 15 km |
| Bellandur–Marathahalli belt | 15 km |
| MG Road / city centre | 25 km |
| Outer Ring Road / Manyata | 29 km |
| Kempegowda Int'l Airport | 40 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.