RERA Property Intelligence Report · Preview

Godrej 24

Manyata Industrial Parks · Anekal · K-RERA PRM/KA/RERA/1251/308/PR/190523/002566

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

439
Registered units
₹243.0 Cr
Est. construction cost
Units profiled
45
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units439Total inventory registered with K-RERA.
Registered land area24,331 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.247Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings5Official tower/wing count in the K-RERA detail page.
Parking disclosed415 total (52 open) — 0.95 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date01-09-2019

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A22110109-
B187473-
C157268-
D187473-
E2210992-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 439 official flat/unit rows, matching the 439 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK23987.3-114.9 sqm43.4-58.0 sqm239
2BHK14369.6-70.8 sqm35.2-35.7 sqm143
1BHK5743.9-45.0 sqm20.6-22.8 sqm33 (24 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
A11043.9-97.2 sqm20.6-49.7 sqm109 (1 with 0)
E10943.9-114.9 sqm20.6-58.0 sqm92 (17 with 0)
B7445.0-97.2 sqm20.6-49.7 sqm73 (1 with 0)
D7445.0-97.2 sqm20.6-49.7 sqm73 (1 with 0)
C7243.9-97.2 sqm20.6-49.7 sqm68 (4 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A 002A03BHK97.2 sqm49.7 sqm1
A 003A01BHK45.0 sqm20.6 sqm1
A 101A13BHK87.3 sqm43.4 sqm1
A 102A13BHK97.2 sqm49.7 sqm1
A 103A13BHK95.1 sqm49.0 sqm1
A 104A13BHK95.1 sqm49.0 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~870 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a large, multi-tower township — 439 homes across 5 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 415 parking spaces for 439 homes (~0.9 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~41 sqm per home; across all 439 homes that is ~74% of the plot — on the lower side — the undivided shares sum to noticeably less than the plot, worth asking the builder why before relying on it. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 37 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 01 Sep 2024, extended (Covid Extension) to 01 Jun 2025 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
PRASENJIT GHOSH vs MANYATA INDUSTRIAL PARKS LLPRefund of remaining 2.2 lakhs that Godrej has deducted because I cancelled the unit due to medical emergencyAUTHORITY11/01/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (1 complaint listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200912/0006562
12-09-2020
Unfair deduction of 2.2 Lakhs on cancellation of Unit from me and selling it at higher price to other customerGodrej 24DISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectRSP Design Consultants India Pvt. Ltd.,-1996RSP House, Museum Road
Structural engineerDesignTree Service Consultants Pvt. Ltd.,---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹55.4 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Motiwani - Fort (IFSC HDFC0000060, a/c …5082). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub8 km
Bellandur–Marathahalli belt10 km
Electronic City13 km
MG Road / city centre20 km
Outer Ring Road / Manyata23 km
Kempegowda Int'l Airport34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Manyata Industrial.

Other RERA-registered projects in Sarjapura

Major developers building in Sarjapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Godrej 24?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 27 Jul 2026