Bangalore/Project record

K-RERA · the public record

GMC CONFLUENCE

Anekal · Grihamithra Confra

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

7%construction reportedQ1 2026 filing
270units not bookedof 270 · Q1 2026 filing
28 Feb 2031declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q1 2026 to Q1 2026

declared completion

28 Feb 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 BHK
63
3 BHK
207

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.1registered acres

87.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/170426/008589

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion28 February 2031
Land area12,520 sq m (3.1 acres)
Homes registered270
Tower/wing entries3
Unit mix63 × 2 BHK, 207 × 3 BHK

In context

Density87.3 homes per acre
Density in context66th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units270Total inventory registered with K-RERA.
Official carpet area25,110 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area47,001 sqmUseful scale context when comparing density and project cost.
Registered land area12,520 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.749Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)270Separate filed counts; these categories may overlap and are not added together.
Covered-parking field319Separate filed counts; these categories may overlap and are not added together.
Open-parking field36Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberSTRRPA/TP/CC/197/2025-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date06-02-2026
Project start date13-03-2026

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK6323%4,482 sqm
3 BHK20777%20,628 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A1310310344.95 m
Tower B13646444.95 m
Tower C1310310344.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 270 official flat/unit rows, matching the 270 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK20791.8-106.7 sqm31.7-39.6 sqm207
2 BHK6365.1-75.0 sqm21.7-27.2 sqm63

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower A10365.1-103.1 sqm21.7-37.1 sqm103
Tower C10371.5-103.1 sqm25.7-39.6 sqm103
Tower B6474.7-106.7 sqm26.0-38.5 sqm64
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G001Tower A13 BHK94.8 sqm35.9 sqm1
G002Tower A12 BHK67.6 sqm22.6 sqm1
G003Tower A12 BHK65.1 sqm21.7 sqm1
G004Tower A13 BHK92.9 sqm32.0 sqm1
G005Tower A13 BHK102.8 sqm35.2 sqm1
G006Tower A13 BHK91.8 sqm31.7 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

1 of 28 compliance document slots are filed as Not Applicable; the remaining 27 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved23-12-2025GCPL WATER NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved12-02-2025GCPL KSPCB CFE - LETTER.pdf
KSPCB- MOEF (Above 50 Acres)Approved10-03-2025GCPL MOEF LETTER_11zon.pdf
KPTCL- BESCOMApproved04-08-2025GCPL BESCOM NOC.pdf
Fire and SafetyApproved21-12-2024GCPL FIRE Order Certificate.pdf
Airport Authority of IndiaApproved30-09-2024GCPL Airport Authority NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantVishwas Keremutt Rudraradhya2249982016Bengaluru Urban, Karnataka - 560043
EngineerSahana. GAM30969582023Kolar, Karnataka - 563128
ArchitectSantoshCA/2013/611222013Bengaluru Urban, Karnataka - 560073
ContractorGrihamithra Confra Private Limited-2021Bengaluru Urban, Karnataka - 560098

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress7% → 7% (+0 pts)
Units sold/booked as registered0/270 (0%)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹45.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: AU Small Finance Bank. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City13 km
Bellandur–Marathahalli belt15 km
Whitefield IT hub15 km
MG Road / city centre25 km
Outer Ring Road / Manyata29 km
Kempegowda Int'l Airport41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Grihamithra Confra.

Other RERA-registered projects in Sarjapura

Major developers building in Sarjapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.