RERA Property Intelligence Report · Preview
Godrej Properties · Hosakote · K-RERA PRM/KA/RERA/1250/304/PR/210208/003856
Report coverage
K-RERA registry & builder-record report
What this report covers
To confirm directly with the builder
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.
Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Official carpet area | 10,619 sqm | Regulator-disclosed project-level carpet area, not vision-derived room sums. |
| Registered land area | 286,615 sqm | The land area attached to this K-RERA registration. |
| Project start date | 01-01-2021 |
K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| 30x30 | 127 | 100% | 10,619 sqm |
🔒 Unit-by-unit guidance · Unit Guidance report
Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.
🔒 Full records — land title, amenities paperwork & document catalog · Compliance report
The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.
No litigation declared on this project's K-RERA filing.
21 of 37 compliance document slots are filed as Not Applicable; the remaining 16 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 31 Dec 2025 — which has passed with no OC on file.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA complaint orders (2 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| POORNI VENKATESAN vs Godrej woodland | Direct the Respondant to expedite the construction and development of the project "Godrej Woodland" and to had over the legal physical possession of the Schedule Property i.e., Plot No GDWL1E0784 | AUTHORITY | 20/05/2026 |
| SUMAN DUNDLODIA vs GODREJ PROPERTIES LTD | REFUND OF MONEY PAID BY ME RS 501101/- (FIVE LAKHS ONE THOUSAND ONE HUNDRED ONE ONLY) | AUTHORITY | 08/07/2023 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
11 further authority slots are marked not applicable by the regulator.
| Authority / NOC | Status | Date | File |
|---|
K-RERA names 1 project professional/vendor row across Architect. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Architect | Studiopod Design Private Limited | - | 2015 | 3 GuruNanak Marg, Bandra West Mumbai 400050 |
Godrej Properties has 29 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Godrej Properties”) (average reported construction progress 47%). 9 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Latest quarterly filing (2025-Q4): ₹0.00 Cr collected from buyers, ₹1.24 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹1.24 Cr) exceeded buyer collections (₹0.00 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.
| Construction progress | 86% → 87% (+1 pts) |
| Buyer collections in available QPRs | ₹0.02 Cr |
| Escrow withdrawals in available QPRs | ₹2.52 Cr (121.88x collections) |
QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.
The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.
K-RERA has 1 project-photo upload.
These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Whitefield IT hub | 7 km |
| Bellandur–Marathahalli belt | 14 km |
| Electronic City | 21 km |
| MG Road / city centre | 23 km |
| Outer Ring Road / Manyata | 23 km |
| Kempegowda Int'l Airport | 29 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
Should you buy in Godrej Woodland?
This page is the free K-RERA filing summary. The full RERA Property Intelligence Report gives you buyer-complaint history, regulatory flags, builder track record, the official unit register, land title, NOCs, and (where the sanctioned plans support it) room-by-room unit data and an annotated site plan. See a real one first:
Sample: Century OneWorld Seraya (plotted) → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Built by Godrej Properties. View Godrej Properties's full track record →
Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.
Own a unit in Godrej Woodland?
Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.
Last checked against the RERA register: 27 Jul 2026