Bangalore/Project record

K-RERA · the public record

GODREJ PARKSHIRE

Hosakote · Godrej Properties

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

3%construction reportedQ1 2026 filing
538units not bookedof 1,132 · Q1 2026 filing
31 Dec 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q4 2025 to Q1 2026

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 BHK
688
3 BHK
444

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

13.6registered acres

83.2registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/304/PR/090126/008393

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2030
Land area55,037 sq m (13.6 acres)
Homes registered1,132
Tower/wing entries5
Unit mix688 × 2 BHK, 444 × 3 BHK

In context

Density83.2 homes per acre
Density in context59th percentile of 112 Hosakote projects (median 79.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units1,132Total inventory registered with K-RERA.
Official carpet area86,565 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area187,034 sqmUseful scale context when comparing density and project cost.
Registered land area55,037 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.499Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries5Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)1,132Separate filed counts; these categories may overlap and are not added together.
Covered-parking field1,206Separate filed counts; these categories may overlap and are not added together.
Open-parking field83Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberCC/445/2025-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date29-12-2025
Project start date01-03-2026

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK68861%45,206 sqm
3 BHK44439%41,359 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A2822622686.75 m
B2822622686.75 m
C2822022086.75 m
D2823023086.75 m
E2823023086.75 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 1,132 official flat/unit rows, matching the 1,132 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK68861.4-78.2 sqm27.0-34.3 sqm688
3 BHK44488.3-99.1 sqm39.8-44.5 sqm444

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
D23068.1-99.1 sqm30.1-44.5 sqm230
E23068.1-99.1 sqm30.1-44.5 sqm230
A22661.4-88.9 sqm27.0-40.3 sqm226
B22661.4-88.9 sqm27.0-40.3 sqm226
C22061.4-88.9 sqm27.0-40.3 sqm220
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A0001A02 BHK75.0 sqm32.8 sqm1
A0002A02 BHK68.3 sqm30.2 sqm1
A0003A02 BHK68.3 sqm30.2 sqm1
A0101A13 BHK88.9 sqm40.3 sqm1
A0102A12 BHK68.3 sqm30.2 sqm1
A0103A12 BHK68.3 sqm30.2 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 1 of 28 compliance document slots are filed as under process / not yet usable: Organization Structure.

1 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (4 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Akanksha vs Godrej PropertiesDirect the Respondent to refund the entire amount paid by the Complainant for Unit GHKE1702 without any forfeiture or deduction, along with applicable interest for the period of delay.AUTHORITY31/07/2026
Rakesh S vs Godrej Parkshire1. Full refund of the principal amount of Rs.6,71,488.58. 2. Interest at the rate of SBI MCLR + 2% per annum from Feb 21, 2026, until realization. 3. Compensation of Rs.50,000 for litigation expenseAUTHORITY05/05/2026
Divya H vs Godrej Parkshire1. Full refund of the principal amount of Rs.5,91,765. 2. Interest at the rate of SBI MCLR + 2% per annum from Feb 21, 2026, until realization. 3. Compensation of Rs.50,000AUTHORITY05/05/2026
Rajesh Arya vs GODREJ pARKSHIRE1. Full refund of the principal amount of Rs.9,37,898. 2. Interest at the rate of SBI MCLR + 2% per annum from Feb 14, 2026, until realization. 3. Compensation of Rs.50,000 for litigation expenses andAUTHORITY04/05/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (10 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200108/0005167
08-01-2020
Refund of Booking AmountGodrej Aqua (another project by this promoter)DISPOSED AO
CMP/210207/0007592
07-02-2021
Request for complete refund on cancellation of Sale Process with M/s. Godrej Properties Limited in respect of Apartment bearing Flat No: GDAQC104 at Godrej Aqua Project, BengaluruGodrej Aqua (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/211112/0008548
12-11-2021
AS NO BANK IS APPROVING THE PROJECT I HAVE NO CONFIDENCE TO FOR LOAN WITH LANDERS LIKE GODREJ HOUSING FINANCE / I WISH TO PROCEED WITH BANK ONLY FOR PLOT LOANGodrej Woodland (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220112/0008784
12-01-2022
COMPLAINT UNDER SECION 31 AND 14(2) IN FRONT OF THE ADJUDICATION AUTHORITYGodrej Aqua (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/220117/0008812
17-01-2022
To refund the Booking amount of Rs. 7,60,142.14Godrej Aqua (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/220222/0009039
22-02-2022
REFUND OF DEPOSIT AMOUNT AND COMPENSATIONGodrej Aqua (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/220510/0009445
10-05-2022
refund of the amount paidGODREJ PARK RETREAT (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220510/0009449
10-05-2022
Refund of booking amount paid in march 2022, with interestGODREJ PARK RETREAT (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantBHAVESH D SHAH1216032009Mumbai City, Maharashtra - 400602
EngineerB E PruthvirajaBCCL/BL-3.6/SE-0061/21-222021Bengaluru Urban, Karnataka - 560083
ArchitectShreyas MCA/2012/569572012Bengaluru Urban, Karnataka - 560076
ContractorGodrej Properties Limited-1985Bengaluru Urban, Karnataka - 560038

Builder track record

RERA filing

Godrej Properties has 29 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Godrej Properties”) (average reported construction progress 47%). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹111.41 Cr collected from buyers, ₹27.76 Cr withdrawn from the project's escrow account.

Construction progress1% → 3% (+2 pts)
Units sold/booked as registered594/1132 (52%)
Buyer collections in available QPRs₹218.60 Cr
Escrow withdrawals in available QPRs₹27.76 Cr (0.13x collections)
  • Construction progress moved from 1% to 3% across the filed QPR window.
  • The builder has drawn 0.13x of buyer collections from escrow (about 13% of the ₹219 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹67.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank M G Road, Bangalore IFSC Code : UTIB0000009 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub9 km
Bellandur–Marathahalli belt16 km
Outer Ring Road / Manyata18 km
Kempegowda Int'l Airport19 km
MG Road / city centre21 km
Electronic City26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Godrej Properties. View Godrej Properties's full track record →
Godrej Properties has 18 projects registered in Bangalore, 3 completed, 2 past RERA deadline.
33 complaints on the K-RERA register against Godrej Properties in Bangalore.

Other projects by this builder in Bangalore

Godrej Woodland
Past deadline · 88% built
Godrej Woodland Phase 2
Past deadline · 88% built
Boulevard At Godrej Woodscapes
No filings
Godrej Florenne Phase II
No filings
Godrej Lakeside Orchard
On track · 27% built · 86% sold

Other RERA-registered projects in Krishnarajapuram

Trifecta Verdeen Resplandor ROW House Phase-3

Major developers building in Krishnarajapuram

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.