SHRIRAM BLUE

MAARS INFRA DEVELOPERS · Bengaluru East · K-RERA PRM/KA/RERA/1251/446/PR/180728/001966

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

471
Registered units
₹319.8 Cr
Est. construction cost
Units profiled
43
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units471Total inventory registered with K-RERA.
Official carpet area44,157 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area34,756 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~1.93Sanctioned floor-area ratio (≈67,081 sqm sanctioned FAR area ÷ 34,756 sqm land) — higher means a denser vertical build.
Registered towers/wings11Official tower/wing count in the K-RERA detail page.
Parking disclosed550 total (75 open) — 1.17 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date16-07-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
APARTMENTS471100%44,157 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A124250-
B124250-
C124250-
D124250-
E124250-
F124850-
G124250-
H124250-

Showing first 8 of 11 tower/wing rows.

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 471 official flat/unit rows, matching the 471 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK240101.5 sqm0.2 sqm240
2BHK12680.4-81.1 sqm0.2 sqm126
Duplex5781.5 sqm0.3 sqm114
1 BHK4838.7 sqm0.1 sqm48

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
F4838.7 sqm0.1 sqm48
J4580.4-101.5 sqm0.2-0.3 sqm48
A4281.1-101.5 sqm0.2-0.3 sqm48
B4281.1-101.5 sqm0.2-0.3 sqm48
C4281.1-101.5 sqm0.2-0.3 sqm48
D4281.1-101.5 sqm0.2-0.3 sqm48
E4281.1-101.5 sqm0.2-0.3 sqm48
G4281.1-101.5 sqm0.2-0.3 sqm48
H4281.1-101.5 sqm0.2-0.3 sqm48
K4281.1-101.5 sqm0.2-0.3 sqm48
L4281.1-101.5 sqm0.2-0.3 sqm48
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A.01.01A12BHK81.1 sqm0.2 sqm1
A.01.02A12BHK81.1 sqm0.2 sqm1
A.01.03A13BHK101.5 sqm0.2 sqm1
A.01.04A13BHK101.5 sqm0.2 sqm1
A.02.01A2Duplex81.5 sqm0.3 sqm2
A.02.02A2Duplex81.5 sqm0.3 sqm2

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~938 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a large, multi-tower township — 471 homes across 11 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 550 parking spaces for 471 homes (~1.2 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~0 sqm per home; across all 471 homes that is ~0% of the plot — on the lower side — the undivided shares sum to noticeably less than the plot, worth asking the builder why before relying on it. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 1 of 36 compliance document slots are filed as under process / not yet usable: BWSSB.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 16 Jul 2021, extended (Extension) to 30 Nov 2023 — both dates have passed with no OC on file. The extension on file was granted on 04 Jun 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/220604/001966) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

1 K-RERA order on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (27 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
ANUPAM GUPTA vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDImmediate release of Delay interest, Completion of Project and Possession of unit on or before 16- April-2023AUTHORITY30/10/2023
Rahul Agrawalla & Monica Agarwal vs Maars Infra Developers Private LimitedImmediate release of Delay interest, Completion of Project and Possession of unit on or before 16- April-2023.AUTHORITY30/01/2024
Pramod Kumar Bhargav vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDRequest to take action on builder to provide the delayed compensation on the amount paid until the actual possessionAUTHORITY28/06/2023
Atal vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDI request the Honorable Authority to: Direct the builder to provide all marketing materials and promotional content shared with residents. Conduct a thorough inspection of the project to verify the dAUTHORITY28/03/2025
Saurabh Saxena vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDCompensation for delay in handover. Handover date as per agreement was 16th Jan, 2022. Total amount paid to builder till date is Rs 8451333. Asking for compensation from 17th Jan,2022 till date.AUTHORITY27/09/2023
Nilesh Tiwary vs shriram bluePlease support in getting compensation as we are hard earned money to builderAUTHORITY26/06/2024
Rakesh Agarwal vs SHRIRAM BLUEEither Handover in next 1 month or Compensation 3L for more than 1 year delay from Promised date.AUTHORITY26/06/2024
Hitesh Tanwani vs SHRIRAM BLUETo intervene and help get the handover of my flat as soon as possible as more than 85% of the payment is already paid to the builder. Also, help in getting appropriate compensation as per agreement.AUTHORITY26/06/2024
ABHISHEK GUPTA vs SHRIRAM BLUENeed Help for Compensation for delay in delivery which has already crossed 1 year and more delay is expected , Expected compensation as per SBI MCLR for delay is approx INR 10 Lacs .AUTHORITY26/06/2024
HARSHIT BABBAR vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDTo get Amount refundedAUTHORITY25/06/2022
AMANDEEP & ANUJA vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDcompensation for the delay in possession for the property.AUTHORITY24/01/2024
Ippili Ravikiran vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDThe builder should pay the interest compensation to the buyers since the expiry of the Delivery date which is 16th April 2023AUTHORITY24/01/2024
Vigneswaran Chandramohan & Sivakami Vigneswaran vs Maars Infra Developers Private LimitedPlease help in getting the bedroom flooring done as per the sale agreement.AUTHORITY19/03/2024
Aman Choudhary vs Maars Infra Developers Private LimitedAdditional monthly interest (Sum of 7,91,553) post agreed completion date of 16 Jan 2022.AUTHORITY19/03/2024
THIYAGARAJAN S vs Maars Infra Developers Pvt LtdI am presently without an earning and request RERA to direct Shriram Properties to oblige as per their initial commitment of cancellation amount of INR 25,000 as per booking form and refund paid amounAUTHORITY15/10/2022
Aashish Pradeep Nanavati vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDa) Rs. 28,48,681/- together with interest there on at the rate of 12% per annum from 12.05.2023 until payment b) Rs. 1,00,000/- costs jointly to Complainant and Respondent 2AUTHORITY15/07/2025
Ashish vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDShriram Developers to pay Compensation amount from 16th April 2022 till possession date according to MCLR Rate + 2%. [Mentioned in Sales deed page 5 section O]AUTHORITY14/09/2023
MOHIT RAJ & GUNJAN SAXENA vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDImmediate release of Delay interest, Completion of Project and Possession of unit on or before 16-April-2023AUTHORITY13/08/2024
Vishal Kishalaya Verma & Vijisha vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDRequest Karnataka-Rera to intervene so that possession is expedited and compensation given for the delay period.AUTHORITY13/02/2024
Samarth Jayeshbhai Parikh & Zalak Samarth Parikh vs Maars Infra Developers Private LimitedKindly request the RERA authority to help us get the total compensation Rs. 9,04,954/- as mentioned above from the builder for the delay in providing possession of the apartment.AUTHORITY12/03/2024
Kiron SG & Meghal Patel vs Maars Infra Developers Private LimitedRequesting RERA intervention in getting the delay interest amounting to INR 10,99,752 (Ten Lakhs Ninety Nine Thousand Seven Hundred and Fifty Two) from the builderAUTHORITY10/04/2024
Asha Joseph & Verghese Koshy vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDCompensation Amount = Rs 10,00,000/-AUTHORITY10/01/2025
Naresh Kumar Bathala vs MAARS INFRA DEVELOPERS PRIVATE LIMITED & SHRIRAM PROPERTIES PVT LTDHelp us get the interest on delay period as per Sale Agreement & RERA guidelinesAUTHORITY10/01/2025
Ashish Rastogi vs Maars Infra Developers Private LimitedCompensation for Delay in Completion of ProjectAUTHORITY08/07/2024
ANKUSH SONI & PRIYANKA TIWARI vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDImmediate release of Delay interest and commitment of regular payment of interest on monthly basis till possession , Completion of Project and Possession of unit on or before 16- April-2023.AUTHORITY06/10/2023
RAGIN GANGADHAN vs SHRIRAM BLUEImmediate release of Delay interest, Completion of Project and Possession of unit on or before 16-April-2023AUTHORITY05/06/2024
Beena Guttikar vs MAARS INFRA DEVELOPERS PRIVATE LIMITEDCompensationAUTHORITY02/08/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (4 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190328/0002531
28-03-2019
Refund of Allotment Amount for Cancelled Booking in SHRIRAM BLUESHRIRAM BLUEDISPOSED AO
CMP/190328/0002479
28-03-2019
Refund of Allotment Amount for Cancelled Booking in SHRIRAM BLUESHRIRAM BLUEDISPOSED AO
CMP/210322/0007808
22-03-2021
Amount Not refundedSHRIRAM BLUEDISPOSED AUTHORITY
CMP/191203/0004863
03-12-2019
Booking Cancellation and Paid Amount not being refundedSHRIRAM BLUEDISPOSED AUTHORITY BENCH5

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 1 project professional/vendor row across Architect. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectKhan Global Engineering Consultants Pvt. Ltd-2003HAL 2ND STAGE, INDRANAGAR

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹67.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: YES BANK Kasturba Road (IFSC YESB0000022, a/c …4544). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub6 km
Bellandur–Marathahalli belt10 km
Outer Ring Road / Manyata12 km
MG Road / city centre14 km
Electronic City20 km
Kempegowda Int'l Airport20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Maars Infra.

Other RERA-registered projects in Krishnarajapuram

Trifecta Verdeen Resplandor ROW House Phase-3

Major developers building in Krishnarajapuram

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.