Bangalore/Project record

K-RERA · the public record

Brigade Lakecrest

Bengaluru East · Brigade Enterprises

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

18%construction reportedQ1 2026 filing
252units not bookedof 604 · Q1 2026 filing
31 Mar 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Mar 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BEDROOM + 3 TOILET
22
2 BEDROOM + 2 TOILET
17
3 BEDROOM + 3 TOILET
22
2 BEDROOM + 2 TOILET
20
2 BEDROOM + 2 TOILET
22
2 BEDROOM + 2 TOILET
1
3 BEDROOM + 3 TOILET + MAIDS ROOM / HOME OFFICE
22
3 BEDROOM + 3 TOILET
22
2 BEDROOM + 2 TOILET
22
3 BEDROOM + 3 TOILET
22
2 BEDROOM + 2 TOILET
22
2 BEDROOM + 2 TOILET
21
STUDIO
20
2 BEDROOM + 2 TOILET + STUDY
22
STUDIO
20
2 BEDROOM + 2 TOILET
17
3 BEDROOM + 3 TOILET
85
2 BEDROOM + 2 TOILET + STUDY
20
STUDIO
20
2 BEDROOM + 2 TOILET
22
3 BEDROOM + 3 TOILET
17
3 BEDROOM + 3 TOILET
1
1 BEDROOM + 1 TOILET
22
1 BEDROOM + 1 TOILET
20
3 BEDROOM + 3 TOILET
21
3 BEDROOM + 3 TOILET + MAIDS ROOM / HOME OFFICE
41
3 BEDROOM + 3 TOILET + MAIDS ROOM / HOME OFFICE
21

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

6.9registered acres

87.2registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/240625/007866

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2030
Land area28,024 sq m (6.9 acres)
Homes registered604
Tower/wing entries4
Unit mix212 × 3 BEDROOM + 3 TOILET, 164 × 2 BEDROOM + 2 TOILET, 84 × 3 BEDROOM + 3 TOILET + MAIDS ROOM / HOME OFFICE, 60 × STUDIO, 42 × 2 BEDROOM + 2 TOILET + STUDY, 42

In context

Density87.2 homes per acre
Density in context69th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units604Total inventory registered with K-RERA.
Official carpet area55,763 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area114,509 sqmUseful scale context when comparing density and project cost.
Registered land area28,024 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries4Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)553Separate filed counts; these categories may overlap and are not added together.
Covered-parking field674Separate filed counts; these categories may overlap and are not added together.
Open-parking field9Separate filed counts; these categories may overlap and are not added together.
Garage field683Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Addl.Dir/JDNORTH/0094/24-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date04-06-2025
Project start date01-07-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BEDROOM + 3 TOILET224%107 sqm
2 BEDROOM + 2 TOILET173%90 sqm
3 BEDROOM + 3 TOILET224%98 sqm
2 BEDROOM + 2 TOILET203%79 sqm
2 BEDROOM + 2 TOILET224%85 sqm
2 BEDROOM + 2 TOILET10%82 sqm
3 BEDROOM + 3 TOILET + MAIDS ROOM / HOME OFFICE224%130 sqm
3 BEDROOM + 3 TOILET224%115 sqm
2 BEDROOM + 2 TOILET224%84 sqm
3 BEDROOM + 3 TOILET224%114 sqm
2 BEDROOM + 2 TOILET224%77 sqm
2 BEDROOM + 2 TOILET213%92 sqm
STUDIO203%31 sqm
2 BEDROOM + 2 TOILET + STUDY224%95 sqm
STUDIO203%31 sqm
2 BEDROOM + 2 TOILET173%81 sqm
3 BEDROOM + 3 TOILET8514%113 sqm
2 BEDROOM + 2 TOILET + STUDY203%93 sqm
STUDIO203%31 sqm
2 BEDROOM + 2 TOILET224%79 sqm
3 BEDROOM + 3 TOILET173%111 sqm
3 BEDROOM + 3 TOILET10%121 sqm
1 BEDROOM + 1 TOILET224%48 sqm
1 BEDROOM + 1 TOILET203%46 sqm
3 BEDROOM + 3 TOILET213%102 sqm
3 BEDROOM + 3 TOILET + MAIDS ROOM / HOME OFFICE417%131 sqm
3 BEDROOM + 3 TOILET + MAIDS ROOM / HOME OFFICE213%132 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Wing A2112812865.85 m
Wing B211469565.85 m
Wing C2116316365.85 m
Wing D2216716768.83 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 604 official flat/unit rows, matching the 604 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK29698.4-131.8 sqm42.1-56.0 sqm296
2 BHK20676.7-95.2 sqm33.8-41.0 sqm206
NA6030.6-31.2 sqm12.4-12.7 sqm30 (30 with 0)
1 BHK4246.1-47.6 sqm19.9-20.9 sqm21 (21 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Wing D16779.1-131.1 sqm34.4-55.5 sqm167
Wing C16381.1-115.1 sqm34.8-49.5 sqm163
Wing B14630.6-101.6 sqm12.4-45.8 sqm95 (51 with 0)
Wing A12876.7-131.8 sqm34.1-56.0 sqm128
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A 0003Wing A03 BHK131.8 sqm56.0 sqm1
A 0004Wing A03 BHK130.3 sqm55.3 sqm1
A 0005Wing A03 BHK98.4 sqm42.1 sqm1
A 0006Wing A02 BHK76.7 sqm34.1 sqm1
A 0103Wing A13 BHK131.8 sqm56.0 sqm1
A 0104Wing A13 BHK130.3 sqm55.3 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

⚠ 1 litigation case on record

  • OS — II Addl .Civil Judge, Bangalore Rural (2025)

6 of 33 compliance document slots are filed as Not Applicable; the remaining 27 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (21 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190802/0003774
02-08-2019
Project delay compensation & Veracity of the agreement & Brochure while bookingBrigade Panorama (another project by this promoter)DISPOSED AO
CMP/190915/0004196
15-09-2019
Waiting period more than 1.5 years, amenities built on kharab land, Club house not as per agreementBrigade Panorama (another project by this promoter)DISPOSED AO
CMP/190920/0004245
20-09-2019
Delay in paying the Delay CompensationBrigade Panorama (another project by this promoter)DISPOSED AO
CMP/200211/0005414
11-02-2020
Brigade group not given the compensation as per RERA and changes in the layout planBrigade Panorama (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/200513/0005880
13-05-2020
Refund of amount due to delay in registration/handoverBrigade Panorama (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/201130/0007159
30-11-2020
Brigade has backed out of delay compensation payment after earlier assuring to pay the sameBrigade Panorama (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/210212/0007498
12-02-2021
Recovery of delay compensation, rental loss & Property tax amount with Interest for 6 years of delay caused by builder to deliver possession of flatPlumeria Lifestyle at Brigade Meadows (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/210512/0007948
12-05-2021
BUILDER NOT ALLOWING INSPECTION OF OUR APARTMENTBrigade Buena Vista-Phase 2 (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

3 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved27-03-2008BWSSB NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved03-12-2014KSPCB.pdf
KSPCB- MOEF (Above 50 Acres)Approved27-11-2014SEIAA.pdf
KPTCL- BESCOMApproved09-07-2015BESCOM.pdf
Fire and SafetyApproved05-08-2024Fire NOC Brigade Lake Crest.pdf
Airport Authority of IndiaApproved20-09-2024AAI NOC latest.pdf
BSNL/Telecommunication DepartmentApproved03-07-2009BSNL.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantR. Srinivasan289862000Bengaluru Urban, Karnataka - 560003
EngineerYogeshBCC – BL/3.6-STRL.E.67:09-102010Bengaluru Urban, Karnataka - 560078
ArchitectTILAK THOMASCA/99/252821992Bengaluru Urban, Karnataka - 560001
ContractorBrigade Inhouse-1986Bengaluru Urban, Karnataka - 560055

Builder track record

RERA filing

Brigade has 60 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Brigade Enterprises”) (average reported construction progress 72%). 31 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹50.08 Cr collected from buyers, ₹11.17 Cr withdrawn from the project's escrow account.

Construction progress10% → 18% (+8 pts)
Units sold/booked as registered352/604 (58%)
Buyer collections in available QPRs₹140.32 Cr
Escrow withdrawals in available QPRs₹41.85 Cr (0.30x collections)
  • Construction progress moved from 10% to 18% across the filed QPR window.
  • The builder has drawn 0.30x of buyer collections from escrow (about 30% of the ₹140 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹60.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: KOTAK MAHINDRA BANK Lavelle Road IFSC Code : KKBK0000422 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub7 km
Bellandur–Marathahalli belt10 km
Outer Ring Road / Manyata11 km
MG Road / city centre13 km
Kempegowda Int'l Airport19 km
Electronic City21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Brigade Enterprises. View Brigade Enterprises's full track record →
Brigade Enterprises has 49 projects registered in Bangalore, 9 completed.

Other projects by this builder in Bangalore

Brigade Laguna
Filing overdue · 100% built · 100% sold
Brigade Oak Tree Place
Filing overdue · 100% built
Pearl At Brigade Atmosphere
Filing overdue · 100% built · 100% sold
Azalea At Brigade Meadows
No filings
Brigade Komarla Heights
On track · 100% built · 100% sold
Brigade Nanda Heights
On track · 100% built · 99% sold

Other RERA-registered projects in Krishnarajapuram

Trifecta Verdeen Resplandor ROW House Phase-3

Major developers building in Krishnarajapuram

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Brigade Lakecrest?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026