K-RERA · the public record
Godrej Woodscapes
Bengaluru East · Godrej Properties
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Promoter-reported construction
K-RERA quarterly filings · Q3 2025 to Q1 2026
declared completion
31 Jan 2029
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
11.2registered acres
193.5registered units per acre
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project · Prestige Park Grove
A larger advertised area. Almost the same carpet area.
In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.
This illustrates the report format. These findings concern the named sample, not this project.
Read the sample report ↗
The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1251/446/PR/170524/006882
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
In context
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered units | 2,168 | Total inventory registered with K-RERA. |
| Official carpet area | 200,479 sqm | Regulator-disclosed project-level carpet area, not vision-derived room sums. |
| Official built-up area | 320,585 sqm | Useful scale context when comparing density and project cost. |
| Registered land area | 45,352 sqm | The land area attached to this K-RERA registration. |
| Sanctioned FAR/FSI | 3.247 | Higher FAR generally means a denser vertical build, subject to site layout and open-space design. |
| Registered tower/wing entries | 13 | Official tower/wing count in the K-RERA detail page. |
| Parking total (reconciled) | 2,168 | Separate filed counts; these categories may overlap and are not added together. |
| Covered-parking field | 2,257 | Separate filed counts; these categories may overlap and are not added together. |
| Open-parking field | 217 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Approved plan number | BDA/TPM/DLP-16/22-23/1358/23-24 | Use this to match the sanctioned drawing set shown by the builder. |
| Plan approval date | 29-09-2023 | |
| Project start date | 31-01-2024 |
Official inventory & towers
RERA filingK-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| 1 BHK | 6 | 0% | 274 sqm |
| 2 BHK | 480 | 22% | 33,915 sqm |
| 1BT-EWS | 160 | 7% | 1,735 sqm |
| 2.5 BHK | 11 | 1% | 1,184 sqm |
| 4 BHK | 77 | 4% | 12,073 sqm |
| 3 BHK | 1,434 | 66% | 150,824 sqm |
Registered tower / wing summary
| Tower/wing | Floors | Units | Parking | Height |
|---|---|---|---|---|
| Tower D | 39 | 158 | 158 | 118.4 m |
| E | 39 | 158 | 158 | 118.4 m |
| F | 39 | 158 | 158 | 118.4 m |
| G | 39 | 150 | 150 | 118.4 m |
| H | 39 | 150 | 150 | 118.4 m |
| J | 39 | 150 | 150 | 118.4 m |
| K | 39 | 150 | 150 | 118.4 m |
| L | 39 | 236 | 236 | 120.4 m |
Showing first 8 of 13 tower/wing rows.
Official unit register
RERA filingK-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 2,168 official flat/unit rows, matching the 2,168 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.
By unit type
| Unit type | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| 3 BHK | 1,436 | 69.8-138.5 sqm | 25.6-50.9 sqm | 1,436 |
| 2 BHK | 480 | 66.6-110.6 sqm | 24.4-40.6 sqm | 480 |
| 1BT-EWS | 160 | 9.6-11.6 sqm | 3.5-4.3 sqm | 160 |
| 4 BHK | 77 | 96.8-160.9 sqm | 35.5-59.1 sqm | 77 |
| 2.5 BHK | 9 | 80.6-132.7 sqm | 29.6-48.7 sqm | 9 |
| 1 BHK | 6 | 45.6 sqm | 16.8 sqm | 6 |
By tower / wing
| Tower/wing | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| L | 236 | 9.9-154.3 sqm | 3.6-56.7 sqm | 236 |
| N | 200 | 9.6-160.9 sqm | 3.5-59.1 sqm | 200 |
| M | 196 | 9.6-132.7 sqm | 3.5-48.7 sqm | 196 |
| E | 158 | 85.3-112.7 sqm | 31.3-41.4 sqm | 158 |
| F | 158 | 85.3-112.7 sqm | 31.3-41.4 sqm | 158 |
| Tower D | 158 | 85.3-112.7 sqm | 31.3-41.4 sqm | 158 |
| A | 154 | 45.6-80.6 sqm | 16.8-29.6 sqm | 154 |
| B | 154 | 45.6-80.6 sqm | 16.8-29.6 sqm | 154 |
| C | 154 | 45.6-80.6 sqm | 16.8-29.6 sqm | 154 |
| G | 150 | 69.6-105.7 sqm | 25.6-38.8 sqm | 150 |
| H | 150 | 69.6-96.8 sqm | 25.6-35.5 sqm | 150 |
| J | 150 | 69.6-96.8 sqm | 25.6-35.5 sqm | 150 |
Showing first 12 of 13 tower/wing groups.
Show sample official unit rows
| Unit | Tower | Floor | Type | Carpet | UDS | Parking |
|---|---|---|---|---|---|---|
| D-00-02 | Tower D | 0 | 2 BHK | 85.3 sqm | 31.3 sqm | 1 |
| D-00-03 | Tower D | 0 | 3 BHK | 112.7 sqm | 41.4 sqm | 1 |
| D-00-04 | Tower D | 0 | 3 BHK | 112.7 sqm | 41.4 sqm | 1 |
| D-01-02 | Tower D | 1 | 2 BHK | 85.3 sqm | 31.3 sqm | 1 |
| D-01-03 | Tower D | 1 | 3 BHK | 112.7 sqm | 41.4 sqm | 1 |
| D-01-04 | Tower D | 1 | 3 BHK | 112.7 sqm | 41.4 sqm | 1 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
⚠ 30 of 45 compliance document slots are filed as under process / not yet usable: Board Resolution for Authorized Signatory/Certificate of Authorization, Organization Structure, Certificate from Chartered Account, Commencement Certificate, Project Specifications and more.
No completion certificate (OC) on file yet — project has not been declared complete.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA complaint orders (4 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| KAMALAKAR GURRAM vs GODREJ PROPERTIES LIMITED | 5% amount which I transferred is Hard earned money , Could you please help me in getting that amount Refunded. Please!!! | AUTHORITY | 23/12/2024 |
| Deepesh Ahuja vs Goodrej Woodscapes | I request KRERA to immediately stop the promoter from making any modification to the approved layout plan (Retail 3 – G+3) and prevent the construction of Towers R & S (G+38) without due approvals and | AUTHORITY | 11/11/2025 |
| RAHUL CHANDRA vs Godrej Properties Limited | Allotment of my unit should be restored. | AUTHORITY | 05/08/2026 |
| Usha Gupta vs Goodrej Woodscrapes | I pray to Karnataka State RERA authority to direct Godrej Properties Limited to strictly adhere to the original RERA approved plan and not approve any new proposal for addition of R & S towers to th | AUTHORITY | 03/11/2025 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (10 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/200108/0005167 08-01-2020 | Refund of Booking Amount | Godrej Aqua (another project by this promoter) | DISPOSED AO |
| CMP/210207/0007592 07-02-2021 | Request for complete refund on cancellation of Sale Process with M/s. Godrej Properties Limited in respect of Apartment bearing Flat No: GDAQC104 at Godrej Aqua Project, Bengaluru | Godrej Aqua (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
| CMP/211112/0008548 12-11-2021 | AS NO BANK IS APPROVING THE PROJECT I HAVE NO CONFIDENCE TO FOR LOAN WITH LANDERS LIKE GODREJ HOUSING FINANCE / I WISH TO PROCEED WITH BANK ONLY FOR PLOT LOAN | Godrej Woodland (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
| CMP/220112/0008784 12-01-2022 | COMPLAINT UNDER SECION 31 AND 14(2) IN FRONT OF THE ADJUDICATION AUTHORITY | Godrej Aqua (another project by this promoter) | DISPOSED AUTHORITY FULLBENCH |
| CMP/220117/0008812 17-01-2022 | To refund the Booking amount of Rs. 7,60,142.14 | Godrej Aqua (another project by this promoter) | DISPOSED AUTHORITY BENCH5 |
| CMP/220222/0009039 22-02-2022 | REFUND OF DEPOSIT AMOUNT AND COMPENSATION | Godrej Aqua (another project by this promoter) | DISPOSED AUTHORITY FULLBENCH |
| CMP/220510/0009445 10-05-2022 | refund of the amount paid | GODREJ PARK RETREAT (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
| CMP/220510/0009449 10-05-2022 | Refund of booking amount paid in march 2022, with interest | GODREJ PARK RETREAT (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Statutory approval status
RERA filing10 further authority slots are marked not applicable by the regulator.
| Authority / NOC | Status | Date | File |
|---|
Project team & certifications
RERA filingK-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Chartered accountant | BHAVESH D | 1216603 | 1234 | Thane, Maharashtra - 400602 |
| Engineer | Madhura Manjrekar | STR840002872 | 1233 | Mumbai City, Maharashtra - 400051 |
| Architect | TILAK THOMAS | CA/99/25282 | 1992 | Bengaluru Urban, Karnataka - 560001 |
| Contractor | M/s.Icon Infrastructures | - | 2004 | Bengaluru Urban, Karnataka - 560094 |
Builder track record
RERA filingGodrej Properties has 29 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Godrej Properties”) (average reported construction progress 46%). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filingLatest quarterly filing (2026-Q1): ₹59.49 Cr collected from buyers, ₹36.49 Cr withdrawn from the project's escrow account.
| Construction progress | 18% → 26% (+8 pts) |
| Units sold/booked as registered | 2161/2168 (100%) |
| Buyer collections in available QPRs | ₹355.75 Cr |
| Escrow withdrawals in available QPRs | ₹426.48 Cr (1.20x collections) |
- 100% of registered units are shown as sold/booked, but no completion certificate is on file yet.
- Construction progress moved from 18% to 26% across the filed QPR window.
- Across available QPR rows, escrow withdrawals are 1.20x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.
Declared construction cost ÷ registered units averages to ₹73.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.
RERA 70% project account is on file: Axis Bank Majestic IFSC Code : UTIB0000693 Pin Code : 560009. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Location & Connectivity
The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Whitefield IT hub | 9 km |
| Outer Ring Road / Manyata | 14 km |
| Bellandur–Marathahalli belt | 14 km |
| Kempegowda Int'l Airport | 17 km |
| MG Road / city centre | 18 km |
| Electronic City | 25 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.