RERA Property Intelligence Report · Preview

SHRIRAM GREEN FIELD PHASE 1

SHRIVISION TOWERS · · K-RERA PRM/KA/RERA/1250/304/PR/171014/001213

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
3
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

935
Registered units
₹388.5 Cr
Est. construction cost
Units profiled
25
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units935Total inventory registered with K-RERA.
Official carpet area76,969 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area55,467 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~3.04Sanctioned floor-area ratio (≈168,437 sqm sanctioned FAR area ÷ 55,467 sqm land) — higher means a denser vertical build.
Registered towers/wings6Official tower/wing count in the K-RERA detail page.
Parking disclosed935 total (181 open) — 1.00 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date01-03-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
APARTMENTS935100%76,969 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A19150150-
B19151151-
C19149149-
D19149149-
E19185185-
F19151151-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 935 official flat/unit rows, matching the 935 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2+Study37576.4-81.1 sqm0.1 sqm375
3BHK29889.2 sqm0.1 sqm298
3 BHK11189.2 sqm0.1 sqm111
2BHK7760.0-73.6 sqm0.0-0.1 sqm77
2+study7380.1-80.1 sqm0.1 sqm73
2 BHK173.6 sqm0.1 sqm1

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
E18560.0-89.2 sqm0.0-0.1 sqm185
B15173.6-89.2 sqm0.1-0.1 sqm151
F15173.6-89.2 sqm0.1-0.1 sqm151
A15060.0-89.2 sqm0.0-0.1 sqm150
C14973.6-89.2 sqm0.1-0.1 sqm149
D14973.6-89.2 sqm0.1-0.1 sqm149
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A - 101A12+Study80.1 sqm0.1 sqm1
A - 102A13BHK89.2 sqm0.1 sqm1
A - 103A13BHK89.2 sqm0.1 sqm1
A - 104A12BHK60.0 sqm0.0 sqm1
A - 105A12+Study76.4 sqm0.1 sqm1
A - 106A12+Study76.4 sqm0.1 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~885 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a large, multi-tower township — 935 homes across 6 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 935 parking spaces for 935 homes (~1.0 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~0 sqm per home; across all 935 homes that is ~0% of the plot — on the lower side — the undivided shares sum to noticeably less than the plot, worth asking the builder why before relying on it. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 21 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Mar 2019, extended (Section 6 Extension) to 30 Mar 2020 — both dates have passed with no OC on file. The extension on file was granted on 22 Jun 2022 (K-RERA extension no. EX/PRM/KA/RERA/1250/304/PR/220622/001213) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (14 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
G Sivasankari vs SHRIVISION TOWERS PVT LTD, SMT. RATHNAMMARefund the compensation and interest amountAUTHORITY31/10/2022
Devyani Vasant Phegade vs SHRIVISION TOWERS PVT LTDDelay interest, compensation, quash illegal demand notes, etc.AUTHORITY31/10/2022
PRABHU KUMAR XAVIER vs SHRIVISION TOWERS PVT LTD, SHRIPROP HOMES PVT LTD(i) Direct respondents to immediately give possession of the scheduled property as per agreement, Delay Compensation compenstion of Rs. 1500000/-for mental harassment, legal cost of Rs. 150000/--AUTHORITY31/10/2022
SUBHAYAN SAHA vs M/S SHRIVISION TOWERS PVT.LTD.Fix all the cracks & compensate for damageAUTHORITY29/12/2022
Atul Kumar Aggarwal vs SHRIVISION TOWERS PVT LTDDelay interest, compensation, othersAUTHORITY28/11/2022
Manish Kumar Agrawal vs SHRIVISION TOWERS PVT LTDQuash demand notes, possession, delay interest, compensation etcAUTHORITY28/11/2022
SANJIV JAISWAL vs SHRIRAM GREEN FIELD PHASE 1Compensation as per RERA ROIAUTHORITY26/07/2022
VIKAS KUMAR MORE vs SHRIVISION TOWERS PRIVATE LIMITED & 6 OTHERSDelay Interest and direct the Respondent to complete the amentitiesAUTHORITY25/06/2024
MONU KUMAR vs SHRIVISION TOWERS PRIVATE LIMITEDPRM/KA/RERA/1250/304/PR/171014/001213AUTHORITY25/06/2022
Abhishek vs SHRIVISION TOWERS PRIVATE LIMITED1. Resolve the issues 2. Remove unfair interest amount. 3. Allot Car Parking. 4. Monthly Delay Compensation For Bank Interest since July 2020.AUTHORITY19/01/2023
RAJ KUMAR MISHRA vs SHRIRAM GREEN FIELD PHASE IPrescribed rate of interest for Delay in handing over possession of apartment unit from date of promised possession i.e., 31/06/2018 till actual handover of possession i.e., 12/10/2019, and legal costAUTHORITY13/05/2024
Shriram Greenfield Delayed Possesion vs SHRIVISION TOWERS PRIVATE LIMITEDCompensation and PossessionAUTHORITY08/06/2023
Minakshi Ghosh vs SHRIVISION TOWERS PRIVATE LIMITEDDelay interest, Compensation, Inspection, OrsAUTHORITY06/09/2024
SANILESH M vs SHRIRAM GREEN FIELD PHASE 1Direct to account entire disbursement of lender and refund excess amount collected and also interest paid to lender for the delayed period.AUTHORITY04/09/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (114 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190410/0002436
10-04-2019
Delay in handover in contractual (fit for possession) condition with no confirmation of compensation for delaySHRIRAM GREEN FIELD PHASE 1DISPOSED AO
CMP/190408/0002584
08-04-2019
[Same as Complaint number- CMP/181202/0001707] Possession Delay & Compensation for the delayed time frameSHRIRAM GREEN FIELD PHASE 1DISPOSED AO
CMP/190414/0002585
14-04-2019
Delay in handover in contractual (fit for possession) condition with no confirmation of compensation for delay.SHRIRAM GREEN FIELD PHASE 1DISPOSED AO
CMP/190517/0002586
17-05-2019
Regarding Delay in Project handover and compensationSHRIRAM GREEN FIELD PHASE 1DISPOSED AO
CMP/190407/0002589
07-04-2019
Delay in possession and CompensationSHRIRAM GREEN FIELD PHASE 1DISPOSED AO
CMP/190408/0002590
08-04-2019
Delay in handover in contractual (fit for possession) condition with no confirmation of actual handover dates as well as adequate compensation for delay.SHRIRAM GREEN FIELD PHASE 1DISPOSED AO
CMP/190407/0002596
07-04-2019
Delayed Possession & compensation requiredSHRIRAM GREEN FIELD PHASE 1DISPOSED AO
CMP/190409/0002612
09-04-2019
Delay in handover in contractual (fit for possession) condition with no clarity of compensation for delay.SHRIRAM GREEN FIELD PHASE 1DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectKadur Krishna Siddharth-2004HRBR 2nd Block, Kalyan Nagar Bangalore
ContractorICONICA CONSTRUCTIONS-2015Indiranagar 2nd Stage, Bangalore
Structural engineerINNOTECH ENGINEERING CONSULT PVT LTD---

Builder track record

RERA filing

Shrivision Towers has 3 other K-RERA-registered projects in our records. 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹41.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Richmond Road, Bangalore (IFSC HDFC0000523, a/c …5597). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Whitefield IT hub11 km
Outer Ring Road / Manyata15 km
Kempegowda Int'l Airport15 km
Bellandur–Marathahalli belt17 km
MG Road / city centre19 km
Electronic City27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Shrivision Towers.
Shrivision Towers has 4 projects registered in Bangalore.

Other projects by this builder in Bangalore

Shriram Green Field Phase 1
No filings
Shriram Green Field Phase 2
No filings
Shriram Green Field Phase 2
No filings

Other RERA-registered projects in Krishnarajapuram

Trifecta Verdeen Resplandor ROW House Phase-3

Major developers building in Krishnarajapuram

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.