Bangalore/Project record

K-RERA · the public record

LS SAKURA

Anekal · LIVING STRUCTURES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

55%construction reportedQ1 2026 filing
78units not bookedof 132 · Q1 2026 filing
31 Dec 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK
88
2 BHK
44

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.1registered acres

61.8registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/120225/007497

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2030
Land area8,650 sq m (2.1 acres)
Homes registered132
Tower/wing entries2
Unit mix88 × 3 BHK, 44 × 2 BHK

In context

Density61.8 homes per acre
Density in context30th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units132Total inventory registered with K-RERA.
Official carpet area11,925 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area27,844 sqmUseful scale context when comparing density and project cost.
Registered land area8,650 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.24Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)132Separate filed counts; these categories may overlap and are not added together.
Covered-parking field195Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberSTRRPA/TP/CC/24/2024-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date13-12-2024
Project start date01-02-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK8867%8,477 sqm
2 BHK4433%3,448 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
WING 111666635.85 m
WING 211666635.85 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 132 official flat/unit rows, matching the 132 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK8893.7-98.1 sqm62.2-65.1 sqm88
2 BHK4478.4 sqm52.0 sqm44

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
WING 16678.4-98.1 sqm52.0-65.1 sqm66
WING 26678.4-96.7 sqm52.0-64.2 sqm66
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
104WING 113 BHK93.7 sqm62.2 sqm1
105WING 112 BHK78.4 sqm52.0 sqm1
106WING 113 BHK98.1 sqm65.1 sqm1
107WING 113 BHK98.1 sqm65.1 sqm1
108WING 112 BHK78.4 sqm52.0 sqm1
109WING 113 BHK96.7 sqm64.2 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

2 of 24 compliance document slots are filed as Not Applicable; the remaining 22 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved22-08-2024Water Noc.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved14-03-2024KSPCB Noc.pdf
KSPCB- MOEF (Above 50 Acres)Approved19-07-2024MOEF NOC.pdf
KPTCL- BESCOMApproved17-02-2024BESCOM Noc with Fee Receipt.pdf
Fire and SafetyApproved05-04-2024FIRE NOC.pdf
Airport Authority of IndiaApproved17-04-2024Airport NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantA Amaranath2136292021Shivamogga, Karnataka - 560038
EngineerS CHANDRASHEKARBCCL/BL-3.6/F-0070/21-222021Bengaluru Urban, Karnataka - 560003
ArchitectVISHWAPRIYA PATTABIRAMANCA/2005/366182005Bengaluru Urban, Karnataka - 560078
ContractorLiving Structures-2023Bengaluru Urban, Karnataka - 560035

Builder track record

RERA filing

Living Structures has 4 other K-RERA-registered projects in our records (average reported construction progress 1%). 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹5.38 Cr collected from buyers, ₹4.71 Cr withdrawn from the project's escrow account.

Construction progress40% → 55% (+15 pts)
Units sold/booked as registered54/132 (41%)
Buyer collections in available QPRs₹24.35 Cr
Escrow withdrawals in available QPRs₹17.30 Cr (0.71x collections)
  • Construction progress moved from 40% to 55% across the filed QPR window.
  • The builder has drawn 0.71x of buyer collections from escrow (about 71% of the ₹24 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹45.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: INDUSIND BANK MG Road IFSC Code : INDB0000008 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City13 km
Bellandur–Marathahalli belt15 km
Whitefield IT hub15 km
MG Road / city centre24 km
Outer Ring Road / Manyata29 km
Kempegowda Int'l Airport41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Living Structures.
Living Structures has 4 projects registered in Bangalore.
2 complaints on the K-RERA register against Living Structures in Bangalore.

Other projects by this builder in Bangalore

LS Mark IX
On track · 1% built · 0% sold

Other RERA-registered projects in Sarjapura

Major developers building in Sarjapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.